IIBA CCBA Exam - Topic 4 Question 21 Discussion

Posted by Caitlin on May 05, 2022 at 09:34 AM

Which stakeholder in the solution assessment task will provide information on technical constraints that could limit the solutions that may be implemented?

Suggested Answer: D

Operational support can provide information on technical constraints that may limit the solutions that can be implemented.

Answer, B is incorrect. Suppliers provide information on the functionality associated with a particular solution option.

Answer, C is incorrect. The sponsor approves the expenditure of resources to purchase or develop a solution and approve the final recommendation.

Answer, A is incorrect. The project manager plans and manages the selection process of the solution.


Get Premium CCBA Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
19 comments · newest first
LA
Laurel 11 months ago
I didn't realize operational support had that much influence!
CH
Christa 11 months ago
Wait, are we sure it's not the project manager? Seems like they should know.
KE
Kelvin 12 months ago
Totally agree, operational support is key here!
MA
Maryln 12 months ago
I think suppliers might have some insights too.
RI
Rima 12 months ago
Definitely operational support! They know the systems inside out.
AD
Adela 1 year ago
Not so sure about that, what if it's the Operational support?
MA
Marti 1 year ago
Totally with you, Project manager is key here!
TR
Tresa 1 year ago
Wait, can the Sponsor really provide that info?
JI
Jina 1 year ago
I think Suppliers might have insights too.
LA
Lashonda 1 year ago
Definitely the Project manager! They know the limits.
BE
Beth 1 year ago
I thought the sponsor would be more focused on funding and goals rather than the technical details.
DE
Deonna 1 year ago
I practiced a similar question, and I feel like operational support could provide valuable info on technical constraints.
TA
Tatum 1 year ago
I'm not so sure, but I remember something about suppliers having insights into technical limitations too.
SA
Salley 1 year ago
I think the project manager might be the right answer since they oversee the whole project and know about constraints.
LE
Lenna 1 year ago
I feel pretty confident about this one. The Encryption Policy is the way to go, and contacting Salesforce is a smart move to make sure everything is set up correctly. Option A is my pick.
PE
Percy 1 year ago
I think pooling resources and specialising are the main advantages. Did we cover that they maximise individual interests as well?
BE
Bernardine 1 year ago
I'm leaning towards Option A - a full daily backup with the previous night's tape taken offsite. That provides both security and easy recovery.
DA
Darrel 1 year ago
I'm feeling confident about this one. The metric they're asking about is the average time an interaction spends in the queue, which is the Average Speed of Answer or ASA. B is the right answer.
ST
Stacey 1 year ago
I remember practicing a question about environmental analysis, but this seems more focused on internal factors. Option B makes the most sense to me.
0/2000 characters

Save Cancel