You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus. Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour. What does the 25 workstations per hour represent in this scenario?
A) Parametric estimate
B) Planning
C) Report project
D) Timeboxing

IIBA CCBA Exam - Topic 1 Question 128 Discussion

Actual exam question for IIBA's CCBA exam
Question #: 128
Topic #: 1
[All CCBA Questions]

You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus. Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour. What does the 25 workstations per hour represent in this scenario?

Show Suggested Answer Hide Answer
Suggested Answer: A

A parametric estimate is an estimate that uses a mathematical model to calculate the expected duration, cost, or quantity of a project activity or component based on historical data and known variables1.A parametric estimate is often used when there is a high degree of similarity between the current project and past projects, and when the project can be measured in standard units, such as hours, meters, or workstations2. In this scenario, the 25 workstations per hour represents a parametric estimate because it uses historical data and a standard unit to calculate the expected quantity of workstations that the project team can install per hour.

The other options are not correct because:

Option B is incorrect.Planning is a process that involves defining the scope, objectives, tasks, deliverables, schedule, resources, and risks of a project or a project component3. Planning is not an estimate, but rather a result of estimation and analysis.

Option C is incorrect. Report project is not a valid term in project management or business analysis.A report is a document that communicates the status, progress, results, or findings of a project or a project component to the relevant stakeholders4. A report is not an estimate, but rather a product of estimation and measurement.

Option D is incorrect. Timeboxing is a technique that involves allocating a fixed amount of time for a specific activity or deliverable, and then adjusting the scope or quality to fit within the time limit. Timeboxing is not an estimate, but rather a method of estimation and prioritization.


Parametric Estimating, section ''Description of Change''

Parametric Estimating: Definition, Formula, Example, Advantages & Disadvantages - Project Management, section ''What is Parametric Estimating?''

Planning, section ''Description of Change''

Report, section ''Description of Change''

[Timeboxing], section ''Description of Change''

Contribute your Thoughts:

0/2000 characters
Francoise
4 days ago
Sounds like planning to me, prioritizing is key!
upvoted 0 times
...
Destiny
9 days ago
Wait, can we really only do 25 per hour? Seems low.
upvoted 0 times
...
Glendora
14 days ago
I agree, it's all about the rate of installation.
upvoted 0 times
...
Blair
19 days ago
That's definitely a parametric estimate!
upvoted 0 times
...
Kristal
24 days ago
I feel like it could be a report project, but that doesn't really fit with the context of installation rates.
upvoted 0 times
...
Roy
29 days ago
This reminds me of a practice question where we discussed timeboxing, but I don't think that's the right answer here.
upvoted 0 times
...
Tori
1 month ago
I'm not entirely sure, but I remember something about planning being related to how we allocate resources, so it could be that too.
upvoted 0 times
...
Brinda
1 month ago
I think the 25 workstations per hour is a parametric estimate since it uses a specific rate to project the total installation time.
upvoted 0 times
...