IIBA CBAP Exam - Topic 2 Question 107 Discussion

Actual exam question for IIBA's CBAP exam
Question #: 107
Topic #: 2
[All CBAP Questions]

Which of the following types of charts shows which resources are needed in the project and allows you to group the resources by project phase or other attributes?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Toshia
4 months ago
Totally agree with D, it’s all about resource grouping!
upvoted 0 times
...
Whitley
4 months ago
Wait, is it really D? I thought it was something else!
upvoted 0 times
...
Catarina
4 months ago
A Pareto chart? Nah, that doesn’t fit this question.
upvoted 0 times
...
Ena
4 months ago
I thought it was C, Gantt charts are super useful too.
upvoted 0 times
...
Luisa
5 months ago
Definitely D, Resource Breakdown Structure is the way to go!
upvoted 0 times
...
Mabel
5 months ago
I definitely recall that Pareto charts are more about prioritizing issues, so I don't think that's it.
upvoted 0 times
...
Kristal
5 months ago
I practiced a similar question, and I feel like the Organizational Breakdown Structure could also relate to resource allocation, but I'm not confident.
upvoted 0 times
...
Mona
5 months ago
I'm not entirely sure, but I remember something about Gantt charts being more about scheduling rather than resource grouping.
upvoted 0 times
...
Jerry
5 months ago
I think the Resource Breakdown Structure might be the right answer since it focuses on resources needed for the project.
upvoted 0 times
...
Tyra
5 months ago
I'm a little confused by the options here. I know Gantt charts are used for scheduling, and Pareto charts are for analyzing data, but I'm not sure how they relate to the resources needed for a project. I'll have to think about this one.
upvoted 0 times
...
Bettyann
5 months ago
Okay, I've got this. The Resource Breakdown Structure is the chart that shows the resources needed for the project and lets you organize them by project phase. I'm confident that's the right answer.
upvoted 0 times
...
Jean
5 months ago
Hmm, I'm not sure about this one. I'm trying to remember the different types of charts we covered in class. Let me think this through step-by-step.
upvoted 0 times
...
Peggie
6 months ago
This looks like a question about project management tools. I think the Resource Breakdown Structure would be the best answer, since it allows you to group resources by project phase or other attributes.
upvoted 0 times
...
Janey
10 months ago
Resource Breakdown Structure? More like 'Resource Breakdown' when I try to manage my team's schedules! But hey, at least it gets the job done.
upvoted 0 times
Kaycee
9 months ago
Yeah, Gantt charts are great for visualizing project timelines.
upvoted 0 times
...
Rose
9 months ago
I prefer using Gantt charts to keep track of resource allocation.
upvoted 0 times
...
Anthony
9 months ago
I hear you, managing resources can be tough sometimes.
upvoted 0 times
...
...
Horace
11 months ago
Resource Breakdown Structure, easy peasy! Now, if only organizing my sock drawer was as straightforward...
upvoted 0 times
Walton
10 months ago
Pareto chart is great for identifying the most important resources in a project.
upvoted 0 times
...
Charlie
10 months ago
I think I prefer Gantt charts for project resource organization.
upvoted 0 times
...
Annita
10 months ago
I agree, Resource Breakdown Structure is definitely the way to go.
upvoted 0 times
...
...
Sheron
11 months ago
Hmm, the Organizational Breakdown Structure is more about the organizational hierarchy, not resource allocation. Pareto charts are for analyzing data, not project resources. I'm going with the Resource Breakdown Structure on this one.
upvoted 0 times
...
Bobbie
11 months ago
Gantt charts are great for visualizing project timelines, but they don't really focus on resource allocation, so I don't think that's the right answer.
upvoted 0 times
Lenna
9 months ago
D) Resource Breakdown Structure
upvoted 0 times
...
Katie
9 months ago
C) Gantt chart
upvoted 0 times
...
Bo
9 months ago
B) Organizational Breakdown Structure
upvoted 0 times
...
Della
10 months ago
A) Pareto chart
upvoted 0 times
...
...
Beckie
11 months ago
The Resource Breakdown Structure seems like the obvious choice here. It allows you to organize resources by project phase or other attributes, which is exactly what the question is asking for.
upvoted 0 times
Vivan
10 months ago
I agree, it allows you to group resources by project phase or other attributes.
upvoted 0 times
...
Rhea
11 months ago
I think the answer is D) Resource Breakdown Structure.
upvoted 0 times
...
...
Vanna
11 months ago
I'm not sure, but I think it might be C) Gantt chart because it also shows resources by project phase.
upvoted 0 times
...
Jennie
12 months ago
I agree with Merrilee, because the Resource Breakdown Structure shows the resources needed in the project.
upvoted 0 times
...
Merrilee
12 months ago
I think the answer is D) Resource Breakdown Structure.
upvoted 0 times
...

Save Cancel