Which of the following situations best applies to an organisation that uses a project, rather than a process, to accomplish its business activities?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Lisha
3 months ago
D sounds like a pretty standard process to me. Acquiring parts from a vendor is part of the regular manufacturing workflow, not a special project.
upvoted 0 times
Elmira
2 months ago
C) A city department sets up a new firefighter training program.
upvoted 0 times
...
Juan
2 months ago
B) A commercial construction company is hired to build a warehouse.
upvoted 0 times
...
Loreen
2 months ago
A) Clothing company designs, makes, and sells a new item.
upvoted 0 times
...
...
Bette
3 months ago
Haha, imagine if a clothing company designed and sold a new item every day. That would be one busy project team!
upvoted 0 times
Rolf
23 days ago
Yeah, that sounds more like a process than a project.
upvoted 0 times
...
Tish
25 days ago
D) A manufacturing organization acquires component parts from a contracted vendor
upvoted 0 times
...
Holley
26 days ago
That would definitely keep the project team on their toes!
upvoted 0 times
...
Leota
27 days ago
A) Clothing company designs, makes, and sells a new item.
upvoted 0 times
...
Mona
1 months ago
That seems more like a process than a project.
upvoted 0 times
...
Launa
1 months ago
D) A manufacturing organization acquires component parts from a contracted vendor
upvoted 0 times
...
Kimberely
2 months ago
Yeah, that sounds more like a project than a process.
upvoted 0 times
...
Stefanie
2 months ago
B) A commercial construction company is hired to build a warehouse.
upvoted 0 times
...
Haley
2 months ago
That would definitely keep them busy!
upvoted 0 times
...
Jessenia
3 months ago
A) Clothing company designs, makes, and sells a new item.
upvoted 0 times
...
...
Wilbert
3 months ago
I'm not so sure. C could also be a valid answer, as setting up a new training program seems more like a project than a regular business process.
upvoted 0 times
Melissia
2 months ago
C) A city department sets up a new firefighter training program.
upvoted 0 times
...
Ruth
2 months ago
A) Clothing company designs, makes, and sells a new item.
upvoted 0 times
...
...
Sherell
3 months ago
But doesn't a project involve a unique goal with a defined start and end date, like designing and selling a new item?
upvoted 0 times
...
Lorrie
3 months ago
I disagree, I believe the answer is B) A commercial construction company is hired to build a warehouse.
upvoted 0 times
...
Sherell
3 months ago
I think the answer is A) Clothing company designs, makes, and sells a new item.
upvoted 0 times
...
Victor
3 months ago
I think the answer is B. A commercial construction company building a warehouse seems like a clear example of a project-based activity, as it has a defined start and end point.
upvoted 0 times
Chauncey
2 months ago
D) A manufacturing organization acquires component parts from a contracted vendor
upvoted 0 times
...
Nettie
2 months ago
C) A city department sets up a new firefighter training program.
upvoted 0 times
...
Thersa
2 months ago
B) A commercial construction company is hired to build a warehouse.
upvoted 0 times
...
Earleen
3 months ago
A) Clothing company designs, makes, and sells a new item.
upvoted 0 times
...
...
Freeman
3 months ago
Because designing, making, and selling a new item sounds like a project to me.
upvoted 0 times
...
Lai
4 months ago
Why do you think so, Freeman?
upvoted 0 times
...
Freeman
4 months ago
I think the answer is A.
upvoted 0 times
...

Save Cancel