IASSC Exam ICGB Topic 1 Question 30 Discussion

Actual exam question for IASSC's IASSC Certified Lean Six Sigma Green Belt exam
Question #: 30
Topic #: 1
[All IASSC Certified Lean Six Sigma Green Belt Questions]

A Belt gathered the following defect data for a shoe production line and wanted to assemble it into a Pareto Chart. The correct order from left to right in the chart would be:

Data:

Cutting38

Forming17

Stitching56

Sealing42

Show Suggested Answer Hide Answer
Suggested Answer: C