During the ______________ phase of 5S is when we might implement a Red Tag program.

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Kristeen
4 months ago
Not sure about that, seems a bit off to me.
upvoted 0 times
...
Estrella
4 months ago
Wait, really? I always thought it was Shining!
upvoted 0 times
...
Fannie
4 months ago
I thought it was Standardizing?
upvoted 0 times
...
Lashawna
4 months ago
Totally agree, that's where it makes the most sense.
upvoted 0 times
...
Sharmaine
5 months ago
It's definitely during the Sorting phase!
upvoted 0 times
...
Mireya
5 months ago
I could be wrong, but I think Standardizing might involve the Red Tag program too, since it’s about maintaining order.
upvoted 0 times
...
Leatha
5 months ago
I'm not entirely sure, but I feel like the Shining phase is more about cleaning rather than sorting out items.
upvoted 0 times
...
Jess
5 months ago
I remember practicing a question about 5S, and Sorting seemed to be the right answer for when we identify what to keep or discard.
upvoted 0 times
...
Ruthann
5 months ago
I think the Red Tag program is related to getting rid of unnecessary items, so it might be during the Sorting phase?
upvoted 0 times
...
Francine
5 months ago
Let me think this through... The Red Tag program is used to identify and remove unnecessary items, so that would make sense to do during the Sorting phase. I'll go with that as my answer.
upvoted 0 times
...
Junita
5 months ago
The Red Tag program is definitely implemented in the Sorting phase of 5S. That's one of the key things we covered in class, so I feel confident about that.
upvoted 0 times
...
Kristeen
5 months ago
Hmm, I'm a little confused on the 5S phases. I think the Red Tag program might be during the Straightening phase, but I'm not 100% certain.
upvoted 0 times
...
Jerry
5 months ago
I'm pretty sure the Red Tag program is implemented during the Sorting phase of 5S, but I'll double-check that in my notes just to be sure.
upvoted 0 times
...
Lisandra
5 months ago
This seems like a straightforward responsive design problem. I'd go with option A and use CSS media queries to adjust the layout at the 800px breakpoint.
upvoted 0 times
...
Tien
5 months ago
I'm pretty confident about this one. I think the answer is A - they are integrated out-of-the-box, so no additional setup is required.
upvoted 0 times
...

Save Cancel