Which two reconfiguration activities are performed without interrupting host access on a VSP Gx00 system? (Choose two.) Choose 2 answers

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

0/2000 characters
Graciela
3 months ago
I thought upgrading always caused some downtime, but I guess not here!
upvoted 0 times
...
Dottie
3 months ago
Yup, adding a DKB is definitely non-disruptive.
upvoted 0 times
...
Desire
3 months ago
Wait, can you really upgrade from G200 to G800 without interrupting? Sounds risky!
upvoted 0 times
...
Janey
4 months ago
Totally agree, those are the right moves!
upvoted 0 times
...
Joanna
4 months ago
Adding a DKB and a DB60 drive tray can be done without downtime.
upvoted 0 times
...
Marisha
4 months ago
I’m leaning towards adding a DKB and a DB60 drive tray, but I’m not 100% confident. I hope I got this right!
upvoted 0 times
...
Noel
4 months ago
I feel like upgrading from G200 to G800 would definitely cause an interruption, but I can't recall if G600 is different.
upvoted 0 times
...
Desmond
4 months ago
I remember practicing a question like this, and I think adding a DB60 drive tray might also be correct.
upvoted 0 times
...
Sina
5 months ago
I think adding a DKB is one of the activities that can be done without interrupting access, but I'm not sure about the second one.
upvoted 0 times
...
Barrett
5 months ago
I've got a good feeling about this one. From what I remember, adding a DKB and adding a DB60 drive tray are the two reconfiguration activities that can be done without interrupting host access on a VSP Gx00 system. I'm confident those are the correct answers.
upvoted 0 times
...
Flo
5 months ago
I'm a little confused by the terminology in this question. I'm not super familiar with the VSP Gx00 system, so I'm not 100% sure what all the different components are. I'll try to eliminate the options that seem less likely, but I may need to guess on this one.
upvoted 0 times
...
Denny
5 months ago
Okay, let me think this through. The question is asking about reconfiguration activities on a VSP Gx00 system that don't interrupt host access. Based on my understanding, adding a DKB and adding a DB60 drive tray are the two that fit that criteria, so I'll go with those.
upvoted 0 times
...
Margart
5 months ago
This one seems pretty straightforward. I think the answer is adding a DKB and adding a DB60 drive tray, since those are the only two options that mention "without interrupting host access".
upvoted 0 times
...
Lanie
5 months ago
Hmm, I'm a bit unsure about this one. I know the question is asking about reconfiguration activities that don't interrupt host access, but I'm not familiar with the specific VSP Gx00 system details. I'll need to review my notes to see if I can narrow down the options.
upvoted 0 times
...
Amber
5 months ago
Hmm, I'm not sure about this one. I'll have to think it through carefully. Maybe I should review my notes on inventory management first.
upvoted 0 times
...
Ronnie
1 year ago
I think upgrading from G200 to G600 might also be done without interrupting host access. It's a lower model upgrade.
upvoted 0 times
...
Larue
1 year ago
I'm not sure about upgrading from G200 to G800. That might cause some interruption.
upvoted 0 times
...
Jesusita
2 years ago
I agree with Skye. Those activities seem like they can be performed seamlessly.
upvoted 0 times
...
Oren
2 years ago
I'm going with A and B too. Upgrading the system model sounds like a recipe for disaster - can you imagine the IT team trying to pull that off without any downtime? Good luck with that!
upvoted 0 times
...
Cristy
2 years ago
Aha! I've got it. A and B are the correct answers. Adding storage components is usually pretty straightforward, but swapping out the whole system model? That's just asking for trouble.
upvoted 0 times
Odette
1 year ago
Yeah, adding a DKB and a DB60 drive tray can be done without interrupting host access.
upvoted 0 times
...
Margurite
1 year ago
I think A and B are the right choices.
upvoted 0 times
...
...
Jerilyn
2 years ago
This is a tricky one! I'm going to go with A and B, since those seem like the least disruptive options. Though I have to admit, the idea of upgrading the system model while users are still accessing it is pretty hilarious.
upvoted 0 times
...
Lucina
2 years ago
Hmm, I'm not too sure about this one. I think adding a DKB might be possible without interruption, but the drive tray addition could be tricky. Let me think about this some more.
upvoted 0 times
Tiera
1 year ago
I believe upgrading from G200 to G800 can also be done without interrupting host access.
upvoted 0 times
...
Glenn
2 years ago
I agree, adding a DKB is definitely one of them. What about the other one?
upvoted 0 times
...
Bulah
2 years ago
I think adding a DKB is one of the activities that can be done without interrupting host access.
upvoted 0 times
...
...
Lucille
2 years ago
A and B seem like the most logical choices here. Upgrading the system model would definitely cause an interruption, so I'm going to rule out C and D.
upvoted 0 times
Glendora
1 year ago
Yes, C and D can be ruled out.
upvoted 0 times
...
Jolene
1 year ago
So, A and B are the correct choices then.
upvoted 0 times
...
Rodrigo
2 years ago
I agree, upgrading the system model would definitely cause an interruption.
upvoted 0 times
...
Dyan
2 years ago
I think adding a DKB and a DB60 drive tray are the reconfiguration activities that can be done without interrupting host access.
upvoted 0 times
...
...
Skye
2 years ago
I think adding a DKB and adding a DB60 drive tray can be done without interrupting host access.
upvoted 0 times
...