GIAC GSLC Exam - Topic 5 Question 28 Discussion
You are the project manager for an important, high-profile project in your matrix structure. The project team members must work with a new technology that most of the team does not have experience with. What should you do in this scenario?
D) Consult with the project team to determine what type of training is needed.
A) Consult with the project sponsor to procure additional, experienced project team members.
B) Consult with the project customer to determine if the scope can be trimmed to meet the current competency level.
C) Consult with functional management in the matrix structure to determine if there are more suitable project team members.