GIAC Exam GCPM Topic 2 Question 4 Discussion

Actual exam question for GIAC's GIAC Certified Project Manager exam
Question #: 4
Topic #: 2
[All GIAC Certified Project Manager Questions]

You work as a project manager for company Inc. You are working on a project that has a budget of $805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have actually spent $430,000 of the budget. Management wants to know the project's cost performance index. Which of the following values will you report?

Show Suggested Answer Hide Answer
Suggested Answer: D