GAQM PPM-001 Exam - Topic 9 Question 72 Discussion

Posted by Elly on Jul 25, 2023 at 08:21 AM

What does a SPI value greater than 1.0 indicate?

Suggested Answer: D

Get Premium PPM-001 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
37 comments · newest first
AR
Arthur 11 months ago
But isn't it possible to have a SPI over 1.0 and still be behind schedule?
PA
Pa 11 months ago
Yep, definitely more work completed!
ER
Erinn 12 months ago
Really? I thought it could mean cost overruns too.
LE
Lemuel 12 months ago
Totally agree, that's a good sign for project progress.
ET
Ethan 12 months ago
A SPI over 1.0 means more work done than planned!
SA
Salome 1 year ago
If I remember correctly, SPI over 1.0 indicates that we've completed more work than planned, which is a good sign for project performance.
AL
Allene 1 year ago
I keep mixing up SPI and CPI. I think SPI greater than 1.0 suggests we're doing well, but I can't recall the exact wording.
KR
Kristin 1 year ago
I remember practicing a similar question, and I think it was about efficiency. A SPI over 1.0 usually indicates we're ahead of schedule, right?
XU
Xuan 1 year ago
I think a SPI value greater than 1.0 means more work was completed than planned, but I'm not entirely sure.
EM
Emile 1 year ago
Okay, let me think this through. I'm leaning towards option C - the payment of consultancy fees to unrelated companies in a foreign jurisdiction. That seems like it could be a potential money laundering indicator.
SK
Skye 1 year ago
This is a tricky one. I'm torn between a few of the options, but I think I'm going to go with A. Avoiding a login screen altogether seems like the best way to keep the signup process simple and user-friendly.
IR
Ira 1 year ago
This looks like a tricky question. I'll need to think carefully about the best practices for Declarative Pipelines.
KA
Kattie 1 year ago
I'd say a SPI over 1.0 means the project team has been working overtime. Or maybe they've just discovered the secret to cloning project managers.
LO
Louis 1 year ago
A SPI greater than 1.0? That's the project manager's dream come true! Time to start planning the celebratory pizza party.
KE
Kenny 1 year ago
↳ replying to Louis
A SPI greater than 1.0 is definitely a reason to celebrate!
MA
Mary 1 year ago
↳ replying to Louis
C) Cost overrun for completed work has occurred
LU
Lucina 1 year ago
↳ replying to Louis
A) More work was completed than planned
LU
Ludivina 2 years ago
Hmm, a SPI over 1.0 indicates a cost underrun. I wonder if the project manager has been skimping on the coffee budget again.
CA
Casey 1 year ago
↳ replying to Ludivina
D) Cost underrun for completed work has occurred
GE
Geoffrey 1 year ago
↳ replying to Ludivina
C) Cost overrun for completed work has occurred
MI
Mireya 1 year ago
↳ replying to Ludivina
B) Less work was completed than planned
LE
Leatha 1 year ago
↳ replying to Ludivina
A) More work was completed than planned
PR
Providencia 1 year ago
↳ replying to Ludivina
Yeah, it's important to keep track of these indicators in project management.
CH
Chantell 1 year ago
↳ replying to Ludivina
Oh really? I didn't know that. Thanks for clarifying.
DE
Deangelo 1 year ago
↳ replying to Ludivina
No, a SPI over 1.0 actually indicates a cost underrun.
ER
Ernie 1 year ago
↳ replying to Ludivina
I think it means more work was completed than planned.
RO
Ronald 2 years ago
Well, duh! A SPI over 1.0 is a clear sign that the project is ahead of schedule. Now if only my boss would understand that.
WE
Wenona 1 year ago
↳ replying to Ronald
I wish my boss would realize that too. It's frustrating when they don't understand project management basics.
CR
Cristal 1 year ago
↳ replying to Ronald
Exactly! A SPI greater than 1.0 means we are ahead of schedule.
LE
Lenita 2 years ago
I'm not sure, but I think it makes sense that if the SPI is greater than 1.0, it means more work was completed than planned.
RE
Reid 2 years ago
I agree with Chu, option A seems to be the correct answer.
BE
Bernadine 2 years ago
A SPI greater than 1.0 means more work was completed than planned. Looks like someone's been burning the midnight oil!
SA
Salena 1 year ago
↳ replying to Bernadine
No, actually a SPI greater than 1.0 means that more work was completed than planned.
CA
Cathern 1 year ago
↳ replying to Bernadine
C) Cost overrun for completed work has occurred
SA
Sabra 1 year ago
↳ replying to Bernadine
That's right! A SPI greater than 1.0 indicates that more work was completed than planned.
AL
Alex 1 year ago
↳ replying to Bernadine
A) More work was completed than planned
CH
Chu 2 years ago
I think a SPI value greater than 1.0 means more work was completed than planned.