What does a SPI value greater than 1.0 indicate?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Kattie
3 months ago
I'd say a SPI over 1.0 means the project team has been working overtime. Or maybe they've just discovered the secret to cloning project managers.
upvoted 0 times
...
Louis
3 months ago
A SPI greater than 1.0? That's the project manager's dream come true! Time to start planning the celebratory pizza party.
upvoted 0 times
Kenny
1 months ago
A SPI greater than 1.0 is definitely a reason to celebrate!
upvoted 0 times
...
Mary
2 months ago
C) Cost overrun for completed work has occurred
upvoted 0 times
...
Lucina
2 months ago
A) More work was completed than planned
upvoted 0 times
...
...
Ludivina
3 months ago
Hmm, a SPI over 1.0 indicates a cost underrun. I wonder if the project manager has been skimping on the coffee budget again.
upvoted 0 times
Casey
29 days ago
D) Cost underrun for completed work has occurred
upvoted 0 times
...
Geoffrey
1 months ago
C) Cost overrun for completed work has occurred
upvoted 0 times
...
Mireya
1 months ago
B) Less work was completed than planned
upvoted 0 times
...
Leatha
1 months ago
A) More work was completed than planned
upvoted 0 times
...
Providencia
1 months ago
Yeah, it's important to keep track of these indicators in project management.
upvoted 0 times
...
Chantell
1 months ago
Oh really? I didn't know that. Thanks for clarifying.
upvoted 0 times
...
Deangelo
2 months ago
No, a SPI over 1.0 actually indicates a cost underrun.
upvoted 0 times
...
Ernie
2 months ago
I think it means more work was completed than planned.
upvoted 0 times
...
...
Ronald
3 months ago
Well, duh! A SPI over 1.0 is a clear sign that the project is ahead of schedule. Now if only my boss would understand that.
upvoted 0 times
Wenona
2 months ago
I wish my boss would realize that too. It's frustrating when they don't understand project management basics.
upvoted 0 times
...
Cristal
2 months ago
Exactly! A SPI greater than 1.0 means we are ahead of schedule.
upvoted 0 times
...
...
Lenita
3 months ago
I'm not sure, but I think it makes sense that if the SPI is greater than 1.0, it means more work was completed than planned.
upvoted 0 times
...
Reid
3 months ago
I agree with Chu, option A seems to be the correct answer.
upvoted 0 times
...
Bernadine
3 months ago
A SPI greater than 1.0 means more work was completed than planned. Looks like someone's been burning the midnight oil!
upvoted 0 times
Salena
2 months ago
No, actually a SPI greater than 1.0 means that more work was completed than planned.
upvoted 0 times
...
Cathern
3 months ago
C) Cost overrun for completed work has occurred
upvoted 0 times
...
Sabra
3 months ago
That's right! A SPI greater than 1.0 indicates that more work was completed than planned.
upvoted 0 times
...
Alex
3 months ago
A) More work was completed than planned
upvoted 0 times
...
...
Chu
4 months ago
I think a SPI value greater than 1.0 means more work was completed than planned.
upvoted 0 times
...