GAQM Exam PPM-001 Topic 9 Question 64 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 64
Topic #: 9
[All PPM-001 Questions]

A project manager has limited authority in which type of organizational structure?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Erick
3 months ago
I bet the project manager in a weak matrix structure wishes they had a stronger matrix to lean on. Just kidding, but that's a good one!
upvoted 0 times
Noe
29 days ago
D) Projectized
upvoted 0 times
...
Ria
30 days ago
C) Balanced matrix
upvoted 0 times
...
Mariko
1 months ago
B) Functional
upvoted 0 times
...
Arthur
1 months ago
A) Weak matrix
upvoted 0 times
...
Rutha
1 months ago
D) Projectized
upvoted 0 times
...
Buck
1 months ago
C) Balanced matrix
upvoted 0 times
...
Galen
2 months ago
B) Functional
upvoted 0 times
...
Elise
2 months ago
A) Weak matrix
upvoted 0 times
...
...
Michael
3 months ago
Hmm, I'm torn between A) Weak matrix and B) Functional. Guess I'll have to review my notes on organizational structures again.
upvoted 0 times
Melissia
3 months ago
That makes sense. Functional structure gives more authority to functional managers.
upvoted 0 times
...
Amie
3 months ago
A) Weak matrix is correct. In this structure, project managers have limited authority.
upvoted 0 times
...
...
Adria
3 months ago
I'm going with C) Balanced matrix. The project manager in a balanced matrix has more authority than in a weak matrix, but less than in a projectized structure.
upvoted 0 times
...
Mickie
3 months ago
I'm not sure, but I think in a functional structure the project manager also has limited authority.
upvoted 0 times
...
Abel
3 months ago
Definitely D) Projectized. In a projectized structure, the project manager has the most authority and control over the project.
upvoted 0 times
...
Franchesca
3 months ago
I agree with Kris, in a weak matrix the project manager has limited authority.
upvoted 0 times
...
Flo
3 months ago
I think the answer is B) Functional. In a functional organization, the project manager has limited authority and must rely on the functional managers to get things done.
upvoted 0 times
Misty
3 months ago
D: Actually, it's A) Weak matrix where the project manager has limited authority.
upvoted 0 times
...
Makeda
3 months ago
C: I believe it's D) Projectized, where the project manager has the most authority.
upvoted 0 times
...
Buddy
3 months ago
B: I think it might be A) Weak matrix, where the project manager has limited authority as well.
upvoted 0 times
...
Dudley
3 months ago
A: I agree, in a functional organization the project manager has limited authority.
upvoted 0 times
...
...
Kris
4 months ago
I think the answer is A) Weak matrix.