GAQM PPM-001 Exam - Topic 9 Question 47 Discussion

The risk register contains which of the following?
A) Identified risks and potential responses
B) Identified risks and updates to scope baseline
C) Risk management plan
D) Risk related contract decisions

GAQM PPM-001 Exam - Topic 9 Question 47 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 47
Topic #: 9
[All PPM-001 Questions]

The risk register contains which of the following?

Show Suggested Answer Hide Answer
Suggested Answer: A

A Risk Register is a Risk Management tool commonly used in Project Management and organizational risk assessments. It acts as a central repository for all risks identified by the project or organization and, for each risk, includes information such as risk probability, impact, counter-measures, risk owner and so on. It can sometimes be referred to as a Risk Log


Contribute your Thoughts:

0/2000 characters
Vincent
8 months ago
I always thought it was just about contracts, but A makes sense.
upvoted 0 times
...
Krystal
9 months ago
Wait, is the risk management plan not part of it?
upvoted 0 times
...
Cathrine
9 months ago
A is correct, no doubt about it!
upvoted 0 times
...
Laquanda
9 months ago
I thought it included updates to scope too?
upvoted 0 times
...
Gladys
9 months ago
Definitely A, it’s all about risks and responses.
upvoted 0 times
...
Adaline
9 months ago
I feel like D might be relevant, but I can’t recall if contract decisions are part of the risk register or not.
upvoted 0 times
...
Flo
9 months ago
I practiced a question similar to this, and I think the risk management plan is a separate document, so I don’t think C is correct.
upvoted 0 times
...
Joni
9 months ago
I think the risk register should definitely include identified risks and potential responses, so I’m leaning towards option A.
upvoted 0 times
...
Delpha
9 months ago
I’m not entirely sure, but I remember something about the risk register not including updates to the scope baseline, so maybe B is wrong?
upvoted 0 times
...
Alease
9 months ago
Hmm, I'm a bit unsure about this one. The options seem quite similar, so I'll need to read them carefully to spot the one that doesn't fit.
upvoted 0 times
...
Joaquin
9 months ago
Purchasing fidelity insurance to protect against a risk sounds like transferring the risk to me. I'm pretty confident that's the right answer here.
upvoted 0 times
...