Which of the following does NOT assess the value a project brings to an organization?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Valentin
1 days ago
Hmm, this is a tricky one. But I think Needs Assessment is more about understanding the problem, not the actual value of the solution. Gotta go with D on this one.
upvoted 0 times
...
Charlene
2 days ago
Benefit cost analysis, net present value, and value analysis all seem to be about evaluating the value a project brings. I'm going to go with D, Needs Assessment, as the odd one out here.
upvoted 0 times
...
Dorathy
4 days ago
I'm not sure about this one. I think it could also be C) Value analysis, as it focuses on analyzing the value of a project.
upvoted 0 times
...
Renay
4 days ago
Haha, nice try! Needs Assessment is all about figuring out what the organization needs, not what the project is worth. I'm going with D on this one.
upvoted 0 times
...
Rene
7 days ago
I'm pretty sure Needs Assessment doesn't evaluate the value a project brings to the organization. That's more about identifying the needs, not the actual value.
upvoted 0 times
...
Omer
9 days ago
I agree with Madonna. Needs assessment focuses on identifying requirements, not assessing value.
upvoted 0 times
...
Madonna
16 days ago
I think the answer is D) Needs assessment.
upvoted 0 times
...