Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 workdays. What should be your concern?
Suggested Answer: B
Get Premium PPM-001 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
BR
Brigette
12 months ago
I think we should focus on that cost overrun first.
LA
Lamar
12 months ago
Definitely a concern about meeting the deadline.
ER
Erasmo
1 year ago
Wait, how can we be 20 days behind if we have 100 EV?
CY
Cyndy
1 year ago
Totally agree, AC is higher than EV.
NI
Nidia
1 year ago
Looks like there's a cost overrun.
AA
Aaron
1 year ago
I’m confused about the terms, but I remember something about cost overruns meaning we're spending more than planned, so B might be correct.
LA
Lashon
1 year ago
I practiced a similar question, and I think the key is that the EV is less than the PV, which suggests we might not meet the deadline, so C seems plausible.
AL
Alpha
1 year ago
I'm not entirely sure, but I feel like the project being behind schedule is a concern too, so D could be relevant.
RU
Ruthann
1 year ago
I think I remember that if the AC is higher than the EV, it indicates a cost overrun, so maybe B is the right choice?
KR
Krissy
1 year ago
I'm a bit unsure about this one. The question mentions extending the EDT, but the solution talks about creating an extension for the CalendarID. I'll need to double-check the details to make sure I understand the right approach.
LA
Lai
1 year ago
The SCOR model is all about supply chain management, so I'm going to focus on that and see if I can figure out the right answer.
TE
Terry
1 year ago
I think we need to assess the event severity and likelihood to calculate risk properly. That makes sense based on past scenarios we've covered.