GAQM PPM-001 Exam - Topic 5 Question 48 Discussion

Which of the following will be required to perform simu-lation for schedule risk analysis?
B) Schedule network diagram and duration estimates
A) Activity list and activity attributes
C) Schedule data and activity resource requirements
D) Milestone list and resource breakdown structure

GAQM PPM-001 Exam - Topic 5 Question 48 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 48
Topic #: 5
[All PPM-001 Questions]

Which of the following will be required to perform simu-lation for schedule risk analysis?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Devorah
8 months ago
Activity resource requirements are key for accurate analysis.
upvoted 0 times
...
Nana
9 months ago
Wait, are you sure all of these are needed? Sounds like a lot!
upvoted 0 times
...
Casie
9 months ago
I disagree, the milestone list isn't really necessary for this.
upvoted 0 times
...
Krissy
9 months ago
I think the activity list is also crucial.
upvoted 0 times
...
Lynda
9 months ago
Definitely need the schedule network diagram and duration estimates!
upvoted 0 times
...
Camellia
9 months ago
I don't think the milestone list is necessary for simulation, but I could be mixing it up with other concepts we studied.
upvoted 0 times
...
Clarinda
9 months ago
I feel like schedule data is crucial for risk analysis, but I can't recall if we need the resource requirements too.
upvoted 0 times
...
Macy
9 months ago
I think we need the schedule network diagram and duration estimates for simulation, but I'm not entirely sure.
upvoted 0 times
...
Cory
9 months ago
I remember practicing a question like this, and I think the activity list is important, but it might not be enough on its own.
upvoted 0 times
...
Dante
9 months ago
Okay, I think I've got a good strategy here. I'll select "Yes" for now, but I'll make a note to come back and review this question if I have time at the end.
upvoted 0 times
...
Bulah
9 months ago
Okay, let's see. I know the question is asking about a type of subsidiary restriction, so I'll focus on the options that mention subsidiaries. I'm leaning towards C. Subsidiary, but I'll double-check the others just to be sure.
upvoted 0 times
...
Fidelia
10 months ago
Hmm, the wording on some of these options is tricky. I want to make sure I don't accidentally select anything about reservations being permanent or guaranteed, since I think that's not always the case.
upvoted 0 times
...

Save Cancel