GAQM PPM-001 Exam - Topic 4 Question 128 Discussion

Which schedule development tool and technique produces a theoretical early start dateand late start date?
A) Critical path method
B) Variance analysis
C) Schedule compression
D) Schedule comparison bar charts

GAQM PPM-001 Exam - Topic 4 Question 128 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 128
Topic #: 4
[All PPM-001 Questions]

Which schedule development tool and technique produces a theoretical early start date

and late start date?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Karima
3 days ago
Wait, are we sure about that? Sounds too simple.
upvoted 0 times
...
Luann
8 days ago
Totally agree, A is the right answer!
upvoted 0 times
...
Rosenda
13 days ago
I thought it was B) Variance analysis.
upvoted 0 times
...
Keneth
18 days ago
It's definitely A) Critical path method!
upvoted 0 times
...
Novella
24 days ago
I’m confused because I thought schedule comparison bar charts were used for visualizing schedules, not for calculating dates. Maybe it’s A as well?
upvoted 0 times
...
Yesenia
29 days ago
I feel like schedule compression is more about shortening the timeline rather than calculating start dates, so I’m leaning towards A) Critical path method.
upvoted 0 times
...
Susana
1 month ago
I remember practicing a question similar to this, and I think it was also about determining start dates. Could it be B) Variance analysis?
upvoted 0 times
...
Celestine
1 month ago
I think the answer might be A) Critical path method, but I'm not entirely sure if it directly gives early and late start dates.
upvoted 0 times
...

Save Cancel