GAQM PPM-001 Exam - Topic 4 Question 128 Discussion

Posted by Laurena on Jun 19, 2026 at 06:31 PM

Which schedule development tool and technique produces a theoretical early start date

and late start date?

Suggested Answer: A

Get Premium PPM-001 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
YO
Yolando 2 months ago
But what about B) Variance analysis? It shows performance, not dates.
DA
Dalene 2 months ago
I agree! It helps identify the earliest and latest starts.
RO
Roslyn 2 months ago
I think it's A) Critical path method. It gives those dates clearly.
EZ
Ezekiel 3 months ago
A) Critical path method is the classic choice for this!
KA
Karima 3 months ago
Wait, are we sure about that? Sounds too simple.
LU
Luann 3 months ago
Totally agree, A is the right answer!
RO
Rosenda 3 months ago
I thought it was B) Variance analysis.
KE
Keneth 3 months ago
It's definitely A) Critical path method!
NO
Novella 3 months ago
I’m confused because I thought schedule comparison bar charts were used for visualizing schedules, not for calculating dates. Maybe it’s A as well?
YE
Yesenia 4 months ago
I feel like schedule compression is more about shortening the timeline rather than calculating start dates, so I’m leaning towards A) Critical path method.
SU
Susana 4 months ago
I remember practicing a question similar to this, and I think it was also about determining start dates. Could it be B) Variance analysis?
CE
Celestine 4 months ago
I think the answer might be A) Critical path method, but I'm not entirely sure if it directly gives early and late start dates.