GAQM PPM-001 Exam - Topic 4 Question 126 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 126
Topic #: 4
[All PPM-001 Questions]

A Project with a total funding of $70,000 finished with a BAC value of $60,000.

What term can best describe the difference of $10,000?

Show Suggested Answer Hide Answer
Suggested Answer: B

The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. BAC represents the revised Cost baseline for the project. So Management Contingency Reserve is true.