Halloween Special 2026! Get Up to 25% OFF Practice Questions! Limited Time - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM PPM-001 Exam - Topic 4 Question 123 Discussion

Posted by Glory on Apr 02, 2026 at 10:21 PM

Which involves estimating the cost of individual work items:

Suggested Answer: B

Bottom-up estimating: Estimating the cost of individual work items and then rolling up the costs to arrive at a project total , more accurate


Get Premium PPM-001 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
PE
Peter 3 months ago
I’m not sure. A) Analogous estimating seems quicker but less accurate.
JU
Julio 3 months ago
I agree, B) is detailed. Helps avoid surprises later.
MI
Mitzie 3 months ago
I think it's B) Bottom up estimating. It breaks down costs well.
GO
Goldie 4 months ago
Totally agree with you, Franchesca! Bottom up is best!
EL
Elouise 4 months ago
Wait, how does square foot estimating even work?
AU
Audry 4 months ago
Definitely A) Analogous estimating for quick estimates!
WI
Winifred 5 months ago
I thought computerized estimating was more reliable?
FR
Franchesca 6 months ago
Bottom up estimating is the way to go for accuracy!
JE
Jess 6 months ago
I’m leaning towards B) Bottom up estimating too, but I wonder if D) Square foot could apply in some contexts.
YA
Yan 7 months ago
I’m a bit lost on this one. I feel like C) Computerized could involve estimating, but it doesn’t specifically mention individual items.
DA
Daniel 7 months ago
I remember practicing a question like this, and I think A) Analogous estimating is more about comparing to previous projects rather than individual items.
AN
Annelle 7 months ago
I think it might be B) Bottom up estimating since it focuses on individual work items, but I'm not entirely sure.
0/2000 characters

Save Cancel