GAQM PPM-001 Exam - Topic 3 Question 10 Discussion

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
D) Estimate Activity Resources
A) Control Schedule
B) Define Activities
C) Develop Schedule

GAQM PPM-001 Exam - Topic 3 Question 10 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 10
Topic #: 3
[All PPM-001 Questions]

Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Nan
10 months ago
Just to clarify, RBS is part of resource estimation.
upvoted 0 times
...
Dino
10 months ago
Wait, are we sure about that? Seems off.
upvoted 0 times
...
Phil
10 months ago
Totally agree, it's D!
upvoted 0 times
...
Darell
11 months ago
I thought it was C, Develop Schedule.
upvoted 0 times
...
Reed
11 months ago
It's definitely D, Estimate Activity Resources.
upvoted 0 times
...
Ronnie
11 months ago
I’m leaning towards "Estimate Activity Resources" since it seems to fit with resource requirements, but I’m not completely confident.
upvoted 0 times
...
Felicidad
11 months ago
I feel like the RBS is more related to defining activities, but I could be mixing it up with another concept.
upvoted 0 times
...
Azalee
11 months ago
I think the outputs like activity resource requirements and RBS are linked to the process of estimating resources, but I'm not entirely sure.
upvoted 0 times
...
Hyman
11 months ago
I remember practicing a similar question, and I think it was about developing the schedule. But this one feels different.
upvoted 0 times
...
Darrin
11 months ago
Hmm, I'm a bit confused on this one. I know Fedora uses RPM packages, but I can't remember if the dependency manager was yum or dnf. I'll have to think this through carefully.
upvoted 0 times
...
Roslyn
11 months ago
I'm a bit confused by this question. How exactly does currency appreciation impact different businesses? I'll need to think this through carefully.
upvoted 0 times
...
Regenia
11 months ago
I'm a bit confused on this one. I'll need to review the material on configuration functions again.
upvoted 0 times
...