GAQM CSM-001 Exam - Topic 5 Question 109 Discussion

Posted by Becky on Apr 02, 2026 at 06:07 PM

Who is ultimate responsible for the Product Backlog item estimates?

Suggested Answer: D

Get Premium CSM-001 Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
JE
Jenifer 3 months ago
But the Development Team does the actual work. They should estimate their tasks.
TH
Theola 3 months ago
I disagree. The Project Owner should have the final say on estimates.
UN
Una 3 months ago
I think it's definitely the Development Team. They know the work best.
LO
Loreen 4 months ago
I’m not convinced, seems like a shared responsibility to me.
AL
Alesia 4 months ago
Totally agree, the Development Team knows the work best!
ED
Edelmira 4 months ago
Wait, are we sure it's not the Scrum Master?
RE
Reena 5 months ago
I thought the Product Owner had the final say on estimates?
RU
Rupert 6 months ago
It's definitely the Development Team that estimates the items.
MA
Ma 6 months ago
I’m confused about this one. I thought stakeholders had input, but I don’t think they’re the ones who estimate the backlog items.
TY
Tyisha 7 months ago
I’m leaning towards the Product Owner being responsible, but I recall something about the Development Team having a key role too.
TI
Tien 7 months ago
I remember a practice question where the Scrum Master was mentioned, but I think they mainly facilitate rather than estimate.
MA
Marge 7 months ago
I think the Development Team is responsible for the estimates, but I’m not entirely sure. It feels like it could also involve the Product Owner.