The Product Backlog is maintained by:

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Levi
3 months ago
Really? I always thought it was a team effort!
upvoted 0 times
...
Dahlia
3 months ago
Nope, just the Product Owner!
upvoted 0 times
...
Skye
3 months ago
Wait, I thought the Scrum Master had a role in that too?
upvoted 0 times
...
Felicidad
4 months ago
Totally agree, the Product Owner is key here!
upvoted 0 times
...
Alpha
4 months ago
It's definitely the Product Owner who maintains the backlog.
upvoted 0 times
...
Christiane
4 months ago
I feel like the Development Team contributes to the backlog, but they don’t maintain it. Is that right?
upvoted 0 times
...
Yvonne
4 months ago
I’m a bit confused; I thought the Scrum Master had some role in it too, but maybe that’s just for facilitation?
upvoted 0 times
...
Kerrie
4 months ago
I remember practicing a question like this, and I think it was definitely the Product Owner.
upvoted 0 times
...
Jamey
5 months ago
I think the Product Owner is the one who maintains the Product Backlog, but I’m not completely sure.
upvoted 0 times
...
Jovita
5 months ago
Okay, I've got this. The Product Backlog is maintained by the Product Owner, so I'm going with option C. Remembering the key responsibilities of the Scrum roles is important for these types of questions.
upvoted 0 times
...
Halina
5 months ago
I'm a bit confused on this one. I know the Product Owner is involved, but I'm not sure if the Scrum Master might also play a role. I'll have to review my notes to make sure I have the right understanding.
upvoted 0 times
...
Bea
5 months ago
Ah, I remember learning about this in class. The Product Backlog is the responsibility of the Product Owner, so I'm confident that C is the correct answer.
upvoted 0 times
...
Blossom
5 months ago
Hmm, I'm a little unsure about this one. I know the Product Owner is responsible for the Product Backlog, but I'm not sure if the Scrum Master might also be involved. I'll have to think this through carefully.
upvoted 0 times
...
Brande
5 months ago
This one seems pretty straightforward. The Product Backlog is maintained by the Product Owner, so I'm going with option C.
upvoted 0 times
...
Sommer
10 months ago
It's like asking who's responsible for the grocery list - the shopper or the person who eats the food. The Product Owner, of course!
upvoted 0 times
...
Jesus
10 months ago
I'm pretty sure the Scrum Master doesn't have any direct involvement in the Product Backlog. That's all on the Product Owner's plate.
upvoted 0 times
Aja
8 months ago
The Product Owner and Scrum Master may collaborate, but ultimately the Product Owner is in charge of the Product Backlog.
upvoted 0 times
...
Mindy
8 months ago
D) The Product Owner and Scrum Master
upvoted 0 times
...
Van
9 months ago
You're right, the Product Owner is responsible for maintaining the Product Backlog.
upvoted 0 times
...
Ludivina
9 months ago
C) The Product Owner
upvoted 0 times
...
Veronika
9 months ago
A) The Scrum Master
upvoted 0 times
...
...
Aimee
10 months ago
C is the correct answer. The Product Owner is solely responsible for managing the Product Backlog.
upvoted 0 times
Precious
9 months ago
C) The Product Owner
upvoted 0 times
...
Jacinta
9 months ago
B) The Development Team
upvoted 0 times
...
Olene
10 months ago
A) The Scrum Master
upvoted 0 times
...
...
Carmen
10 months ago
The Product Backlog is definitely maintained by the Product Owner. They are responsible for managing the backlog and ensuring it aligns with the product vision.
upvoted 0 times
Pamella
9 months ago
D) The Product Owner and Scrum Master
upvoted 0 times
...
Yesenia
10 months ago
That's correct! The Product Owner is responsible for maintaining the Product Backlog.
upvoted 0 times
...
Jacqueline
10 months ago
C) The Product Owner
upvoted 0 times
...
...
Howard
10 months ago
I think it's D) The Product Owner and Scrum Master because they work together to prioritize and manage the backlog.
upvoted 0 times
...
Barrett
11 months ago
I agree with Erinn, the Product Owner is responsible for maintaining the Product Backlog.
upvoted 0 times
...
Erinn
11 months ago
C) The Product Owner
upvoted 0 times
...