GAQM CSM-001 Exam - Topic 3 Question 32 Discussion
What is the Release Burndown?
B) A measure of the remaining Product Backlog across the time of a release plan
A) A graph indicating what has been completed by the Scrum Team
C) What has been completed by the Scrum Team to date
D) The work remaining to be completed by the Product Owner