As the Sprint planning progresses, the workload has grown beyond the development team's capacity. Which action makes most sense for the Team?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Rikki
13 days ago
Working overtime? What is this, the 80s? I'd rather just ditch the Sprint and go home. Oh wait, Option B makes the most sense. My bad.
upvoted 0 times
...
Starr
15 days ago
Option D - recruit additional team members? Seriously? That's like trying to fit a square peg in a round hole. Option B is the clear winner here.
upvoted 0 times
...
Cordelia
17 days ago
Hold up, who said anything about overtime? I'm pretty sure my contract doesn't include mandatory overtime. Option B it is!
upvoted 0 times
...
Edwin
18 days ago
I agree, Option B is the way to go. Canceling the Sprint or working overtime are not sustainable solutions.
upvoted 0 times
...
Gianna
21 days ago
Option B makes the most sense. Collaborating with the Product Owner to adjust the backlog is the appropriate way to manage capacity issues.
upvoted 0 times
...
Marguerita
2 months ago
Starting the Sprint and recruiting additional team members could be a good long-term solution, but collaborating with the Product Owner for now seems more practical.
upvoted 0 times
...
Jaclyn
2 months ago
I agree with Soledad, canceling the Sprint or working overtime doesn't seem like the best solution.
upvoted 0 times
...
Soledad
2 months ago
I think we should collaborate with the Product Owner and potentially remove or change items.
upvoted 0 times
...

Save Cancel