GAQM CSM-001 Exam - Topic 2 Question 26 Discussion
Which three activities will a Product Owner likely engage in during a Sprint?
B) Answer questions from the Development Team about items in the current Sprint and D) Work with the stakeholders and F) Provide feedback
C) Update the Sprint burndown chart
E) Prioritize the Development Team's activities.