What is the major difference between Product Backlog and Sprint Backlog?
C) The Sprint Backlog is a subset of the Product Backlog
A) The Product Backlog is equal to the Sprint Backlog
B) The Product Backlog is a subset of the Sprint Backlog
D) The Sprint Backlog is owned by the Product Owner