What is the correct way to make a change to a contract as a result of a major review of an authorized contract?
A . Incorrect. The Business Relationship Management process is responsible for setting up service review meetings to discuss changes to the service scope, SLA, contract etc. Changes to the contract(s) resulting from these meetings will be subject to the Change Management process.
B . Correct. Any changes to the contract shall be subject to the Change Management process.
C . Incorrect. These representatives will be involved via other processes (e.g. Business Relationship Management process).
D . Incorrect. Supplier Management is responsible for having a process in place for a major review of the contract. Any changes to the contract shall be subject to the Change Management process.
Gayla
10 months agoDeja
11 months agoVallie
11 months agoViola
11 months agoTracie
11 months agoMaile
11 months agoPearlene
11 months agoLauran
11 months agoBecky
11 months agoChau
11 months agoMaia
12 months agoMarsha
12 months ago