What is the correct way to make a change to a contract as a result of a major review of an authorized contract?
A . Incorrect. The Business Relationship Management process is responsible for setting up service review meetings to discuss changes to the service scope, SLA, contract etc. Changes to the contract(s) resulting from these meetings will be subject to the Change Management process.
B . Correct. Any changes to the contract shall be subject to the Change Management process.
C . Incorrect. These representatives will be involved via other processes (e.g. Business Relationship Management process).
D . Incorrect. Supplier Management is responsible for having a process in place for a major review of the contract. Any changes to the contract shall be subject to the Change Management process.
Gayla
9 months agoDeja
9 months agoVallie
9 months agoViola
10 months agoTracie
10 months agoMaile
10 months agoPearlene
10 months agoLauran
10 months agoBecky
10 months agoChau
10 months agoMaia
10 months agoMarsha
10 months ago