To which process shall Problem Management ensure that up-to-date information on Known Errors and corrected Problems is available?
A . Incorrect. According to the standard Problem Management shall make this information available to the Incident Management process, not to all ISO/IEC processes.
B . Incorrect. According to the standard Problem Management shall make this information available to the Incident Management process.
C . Incorrect. According to the standard Problem Management shall make this information available to the Incident Management process.
D . Correct. Problem Management shall make this information available to the Incident Management process, to allow for Incident matching.