Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Exin Exam ASM Topic 9 Question 47 Discussion

Actual exam question for Exin's ASM exam
Question #: 47
Topic #: 9
[All ASM Questions]

After the creation of the Release Plan, the Product Owner says:

Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Mauricio
14 days ago
Wait, the Scrum Master is arguing with the Product Owner? Somebody call the Agile Conflict Resolution team, stat!
upvoted 0 times
...
Benton
1 months ago
Hmm, let me think... 'Fixed requirements and revised estimates'? Nah, that doesn't sound right. B) is the winner, no doubt about it. Gotta love these Scrum-tastic questions!
upvoted 0 times
Sanda
16 hours ago
That's true, completed work is just one factor that can affect the end date.
upvoted 0 times
...
Thaddeus
4 days ago
I agree, the Scrum Master mentioned that changed requirements can impact the release date.
upvoted 0 times
...
Lashaunda
14 days ago
I think B) Changed requirements and revised estimates is the correct answer.
upvoted 0 times
...
...
Rodney
2 months ago
Ah, the age-old battle between Product Owners and Scrum Masters. 'Exactly 240 Story Points' - talk about setting the bar high! B) is the way to go here.
upvoted 0 times
Melissia
29 days ago
B) Changed requirements and revised estimates
upvoted 0 times
...
Ellsworth
1 months ago
A) Changed requirements and estimation mode
upvoted 0 times
...
...
Luther
2 months ago
I initially thought C) Fixed requirements and estimation mode, but then I realized that changed requirements is a key factor that can impact the release date. Good question!
upvoted 0 times
...
Becky
2 months ago
I believe option A) Changed requirements and estimation mode is the correct answer because these factors can cause delays in completing the work.
upvoted 0 times
...
Arlen
2 months ago
I agree with Lisha, changed requirements and estimation mode can definitely impact the end date of the release.
upvoted 0 times
...
Lisha
2 months ago
I think the other two factors are changed requirements and estimation mode.
upvoted 0 times
...
Regenia
2 months ago
The correct answer is B) Changed requirements and revised estimates. The Scrum Master is right - the end date can be impacted by both changed requirements and revised estimates, not just the completed work.
upvoted 0 times
Hyun
1 months ago
A) Changed requirements and estimation mode
upvoted 0 times
...
...

Save Cancel