After the creation of the Release Plan, the Product Owner says:
Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.
The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.
What are the other two factors?