After the creation of the Release Plan, the Product Owner says:
Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.
The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.
What are the other two factors?
Suggested Answer: A
Get Premium ASM Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
36 comments · newest first
DA
Dana
11 months ago
Fixed requirements? That’s a rare find in our projects!
CA
Carli
11 months ago
I’m leaning towards A, but B sounds good too.
AU
Audra
11 months ago
Wait, are we sure about that? What if the requirements stay fixed?
JA
Jacquelyne
12 months ago
Totally agree with you, Jesus!
JE
Jesus
12 months ago
I think it's B, changed requirements and revised estimates.
KE
Keena
12 months ago
I thought it was about changed requirements and estimation mode, but now I'm second-guessing myself. Did we cover this in our last review?
VE
Veronika
1 year ago
I feel like fixed requirements wouldn't really impact the end date as much. Maybe it's about how we estimate the work instead?
SH
Shawana
1 year ago
I'm not entirely sure, but I think revised estimates could be important too. We practiced a question like this in class.
TH
Thurman
1 year ago
I remember we discussed how changing requirements can really affect the timeline. I think that might be one of the factors.
NI
Nina
1 year ago
I'm a little confused by the different options presented. I'll need to carefully read through the details and think through the tradeoffs of each approach before deciding which two solutions I think are the best fit.
CH
Chandra
1 year ago
I've got this! The key is understanding how MPLS encapsulation affects the MTU. I'm pretty confident I can work through this step-by-step.
MA
Mauricio
1 year ago
Wait, the Scrum Master is arguing with the Product Owner? Somebody call the Agile Conflict Resolution team, stat!
GL
Glen
1 year ago
C) Fixed requirements and estimation mode
PH
Phil
1 year ago
B) Changed requirements and revised estimates
RO
Roslyn
1 year ago
A) Changed requirements and estimation mode
BE
Benton
1 year ago
Hmm, let me think... 'Fixed requirements and revised estimates'? Nah, that doesn't sound right. B) is the winner, no doubt about it. Gotta love these Scrum-tastic questions!
ME
Merilyn
1 year ago
So, it seems like B) is the best choice considering the factors mentioned.
EU
Eun
1 year ago
That's true, completed work is just one factor that can affect the end date.
GE
Gerardo
1 year ago
I agree, the Scrum Master mentioned that changed requirements can impact the release date.
LI
Ligia
1 year ago
I think B) Changed requirements and revised estimates is the correct answer.
MA
Maira
1 year ago
Looks like we're all on the same page, B) it is!
SA
Sanda
1 year ago
That's true, completed work is just one factor that can affect the end date.
TH
Thaddeus
1 year ago
I agree, the Scrum Master mentioned that changed requirements can impact the release date.
LA
Lashaunda
1 year ago
I think B) Changed requirements and revised estimates is the correct answer.
RO
Rodney
2 years ago
Ah, the age-old battle between Product Owners and Scrum Masters. 'Exactly 240 Story Points' - talk about setting the bar high! B) is the way to go here.
ME
Melissia
1 year ago
B) Changed requirements and revised estimates
EL
Ellsworth
1 year ago
A) Changed requirements and estimation mode
LU
Luther
2 years ago
I initially thought C) Fixed requirements and estimation mode, but then I realized that changed requirements is a key factor that can impact the release date. Good question!
BE
Becky
2 years ago
I believe option A) Changed requirements and estimation mode is the correct answer because these factors can cause delays in completing the work.
AR
Arlen
2 years ago
I agree with Lisha, changed requirements and estimation mode can definitely impact the end date of the release.
LI
Lisha
2 years ago
I think the other two factors are changed requirements and estimation mode.
RE
Regenia
2 years ago
The correct answer is B) Changed requirements and revised estimates. The Scrum Master is right - the end date can be impacted by both changed requirements and revised estimates, not just the completed work.
LI
Linwood
1 year ago
D) Fixed requirements and revised estimates
GO
Golda
1 year ago
C) Fixed requirements and estimation mode
LE
Lettie
1 year ago
B) Changed requirements and revised estimates
HY
Hyun
1 year ago
A) Changed requirements and estimation mode