After the creation of the Release Plan, the Product Owner says:

Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.

The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.

What are the other two factors?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Mauricio
2 months ago
Wait, the Scrum Master is arguing with the Product Owner? Somebody call the Agile Conflict Resolution team, stat!
upvoted 0 times
Glen
1 months ago
C) Fixed requirements and estimation mode
upvoted 0 times
...
Phil
1 months ago
B) Changed requirements and revised estimates
upvoted 0 times
...
Roslyn
2 months ago
A) Changed requirements and estimation mode
upvoted 0 times
...
...
Benton
3 months ago
Hmm, let me think... 'Fixed requirements and revised estimates'? Nah, that doesn't sound right. B) is the winner, no doubt about it. Gotta love these Scrum-tastic questions!
upvoted 0 times
Merilyn
1 months ago
So, it seems like B) is the best choice considering the factors mentioned.
upvoted 0 times
...
Eun
2 months ago
That's true, completed work is just one factor that can affect the end date.
upvoted 0 times
...
Gerardo
2 months ago
I agree, the Scrum Master mentioned that changed requirements can impact the release date.
upvoted 0 times
...
Ligia
2 months ago
I think B) Changed requirements and revised estimates is the correct answer.
upvoted 0 times
...
Maira
2 months ago
Looks like we're all on the same page, B) it is!
upvoted 0 times
...
Sanda
2 months ago
That's true, completed work is just one factor that can affect the end date.
upvoted 0 times
...
Thaddeus
2 months ago
I agree, the Scrum Master mentioned that changed requirements can impact the release date.
upvoted 0 times
...
Lashaunda
2 months ago
I think B) Changed requirements and revised estimates is the correct answer.
upvoted 0 times
...
...
Rodney
4 months ago
Ah, the age-old battle between Product Owners and Scrum Masters. 'Exactly 240 Story Points' - talk about setting the bar high! B) is the way to go here.
upvoted 0 times
Melissia
3 months ago
B) Changed requirements and revised estimates
upvoted 0 times
...
Ellsworth
3 months ago
A) Changed requirements and estimation mode
upvoted 0 times
...
...
Luther
4 months ago
I initially thought C) Fixed requirements and estimation mode, but then I realized that changed requirements is a key factor that can impact the release date. Good question!
upvoted 0 times
...
Becky
4 months ago
I believe option A) Changed requirements and estimation mode is the correct answer because these factors can cause delays in completing the work.
upvoted 0 times
...
Arlen
4 months ago
I agree with Lisha, changed requirements and estimation mode can definitely impact the end date of the release.
upvoted 0 times
...
Lisha
4 months ago
I think the other two factors are changed requirements and estimation mode.
upvoted 0 times
...
Regenia
4 months ago
The correct answer is B) Changed requirements and revised estimates. The Scrum Master is right - the end date can be impacted by both changed requirements and revised estimates, not just the completed work.
upvoted 0 times
Linwood
2 months ago
D) Fixed requirements and revised estimates
upvoted 0 times
...
Golda
2 months ago
C) Fixed requirements and estimation mode
upvoted 0 times
...
Lettie
2 months ago
B) Changed requirements and revised estimates
upvoted 0 times
...
Hyun
3 months ago
A) Changed requirements and estimation mode
upvoted 0 times
...
...