Exin ASM Exam - Topic 9 Question 28 Discussion

Actual exam question for Exin's ASM exam
Question #: 28
Topic #: 9
[All ASM Questions]

Andy, a Scrum Master, is helping his team draft a Sprint Backlog. In which of the following phases would this

Scrum process be in?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Celestine
4 months ago
I thought they would be reviewing by now, that's surprising!
upvoted 0 times
...
Cherrie
4 months ago
No way, it's all about planning right now.
upvoted 0 times
...
Augustine
4 months ago
Wait, isn't it more about implementing?
upvoted 0 times
...
Selma
4 months ago
I agree, that's where the backlog gets drafted.
upvoted 0 times
...
Dean
5 months ago
Definitely in the Plan and Estimate phase!
upvoted 0 times
...
Louisa
5 months ago
I could be wrong, but I feel like it might be in the Implement phase since they're working on the backlog.
upvoted 0 times
...
Mari
5 months ago
This feels like a practice question I did where we discussed the phases, and I think it aligns with the planning stage.
upvoted 0 times
...
Mabel
5 months ago
I'm not entirely sure, but I remember something about the Sprint Backlog being created before the actual implementation starts.
upvoted 0 times
...
Fausto
5 months ago
I think drafting the Sprint Backlog is part of the planning phase, so maybe it's B?
upvoted 0 times
...
Herminia
5 months ago
I'm a bit confused by the different data source options presented here. I'll need to review my notes on WebLogic Server and Oracle RAC configurations to make sure I understand the differences before selecting an answer.
upvoted 0 times
...
Jules
5 months ago
This seems like a tricky one. I'll need to carefully read through the options and think through the steps to stop the fault messages.
upvoted 0 times
...
Loreta
5 months ago
I'm pretty confident about this one. Factoring is when a business sells its accounts receivable to a third party at a discount, so I think the answer is A.
upvoted 0 times
...
Nobuko
10 months ago
I'd say the Scrum Master is just trying to keep the team from drafting a 'Sprint Backlash' instead of a Sprint Backlog. That'd be a whole different phase, for sure!
upvoted 0 times
...
Julio
10 months ago
B) Plan and Estimate, no doubt. I mean, who drafts a Sprint Backlog during the party at the end of the sprint? That's just crazy!
upvoted 0 times
Lavonna
8 months ago
D) Review and Retrospect
upvoted 0 times
...
Joanne
8 months ago
C) Implement
upvoted 0 times
...
Nada
9 months ago
B) Plan and Estimate
upvoted 0 times
...
Kiley
9 months ago
A) Initiate
upvoted 0 times
...
...
Fredric
10 months ago
D) Review and Retrospect. Isn't the Sprint Backlog reviewed and updated during the sprint retrospective? That's where the Scrum Master comes in.
upvoted 0 times
Annabelle
8 months ago
That's correct. The Scrum Master plays a key role in facilitating the retrospective.
upvoted 0 times
...
Arlean
8 months ago
Yes, the Sprint Backlog is reviewed and updated during the sprint retrospective.
upvoted 0 times
...
Roosevelt
8 months ago
D) Review and Retrospect
upvoted 0 times
...
Luisa
8 months ago
C) Implement
upvoted 0 times
...
Jade
9 months ago
B) Plan and Estimate
upvoted 0 times
...
Francoise
9 months ago
A) Initiate
upvoted 0 times
...
...
Tomoko
10 months ago
I'm going with C) Implement. The Sprint Backlog is the key artifact used during the actual sprint, isn't it?
upvoted 0 times
Annabelle
9 months ago
I see, thanks for clarifying. So, we should be in the Plan and Estimate phase when drafting the Sprint Backlog.
upvoted 0 times
...
Vince
9 months ago
Actually, the Sprint Backlog is created during the Plan and Estimate phase, so the correct answer is B) Plan and Estimate.
upvoted 0 times
...
Rosina
9 months ago
Yes, you are correct. The Sprint Backlog is used during the implementation phase.
upvoted 0 times
...
Eveline
10 months ago
The Sprint Backlog is a list of tasks to be completed during the sprint, so it is created in the Plan and Estimate phase.
upvoted 0 times
...
Tiara
10 months ago
Actually, the Sprint Backlog is created during the Plan and Estimate phase, not during implementation.
upvoted 0 times
...
Loreta
10 months ago
Yes, you are correct. The Sprint Backlog is used during the implementation phase.
upvoted 0 times
...
...
Delfina
11 months ago
B) Plan and Estimate - That's where the Sprint Backlog comes into play. The Scrum Master is helping the team prepare for the upcoming sprint.
upvoted 0 times
Sol
9 months ago
D) Review and Retrospect - Reflecting on what went well and what can be improved for the next sprint.
upvoted 0 times
...
Breana
10 months ago
C) Implement - The team is executing the tasks in the Sprint Backlog.
upvoted 0 times
...
Winfred
10 months ago
B) Plan and Estimate - Yes, the Sprint Backlog is created during this phase to plan out the work for the sprint.
upvoted 0 times
...
Claudia
10 months ago
A) Initiate - This is where the team starts discussing the project and setting goals.
upvoted 0 times
...
Celeste
10 months ago
B) Plan and Estimate - That's where the Sprint Backlog comes into play.
upvoted 0 times
...
Enola
10 months ago
A) Initiate - The team is just starting to plan the sprint.
upvoted 0 times
...
...
Novella
11 months ago
But wouldn't it also involve some implementation tasks? Maybe it could be a mix of Plan and Estimate and Implement phases.
upvoted 0 times
...
Kimbery
11 months ago
I agree with Verda, because in this phase the team plans the work for the upcoming Sprint.
upvoted 0 times
...
Verda
11 months ago
I think drafting a Sprint Backlog would be in the Plan and Estimate phase.
upvoted 0 times
...

Save Cancel