Exin ASM Exam - Topic 8 Question 34 Discussion

Posted by Nan on Oct 24, 2022 at 12:44 AM

Listed below are some risks and issues that might be encountered during the course of a project. Identify

which of the following are risks (not issues).

A) After extensive training, marketing representatives might still not be ready to take orders after the project is

launched.

B) The painting crew might be delayed due to heavy rain, which could negatively impact the project schedule.

C) Funding was not approved.

D) Requirements, as currently defined, are unclear.

Suggested Answer: C

Get Premium ASM Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
33 comments · newest first
GI
Gilma 11 months ago
Heavy rain delaying the crew? Seems a bit far-fetched, right?
DO
Dominga 12 months ago
Totally agree with A and B being risks!
MO
Moira 12 months ago
Wait, are we sure D is a risk? It feels more like an issue.
GO
Golda 12 months ago
I think C is a risk too, funding is crucial!
LE
Lezlie 1 year ago
A and B are definitely risks.
BE
Beata 1 year ago
I practiced a similar question, and I think the answer is A and B, but I’m not confident about D being a risk too.
AB
Abraham 1 year ago
I feel like D could also be a risk because unclear requirements might lead to problems later on.
BE
Belen 1 year ago
I'm not entirely sure, but I think C is more of an issue since it already happened, right?
ST
Stephaine 1 year ago
I remember we discussed risks being potential future problems, so I think A and B are risks.
MI
Micheal 1 year ago
The number of unscheduled change requests could be a useful metric to track, as it might indicate issues with the change management process or a lack of planning.
TE
Tesha 1 year ago
This seems like a straightforward question. I'd go with Event Viewer to find detailed information about the system error.
NI
Nikita 1 year ago
Okay, I need to focus on the key terms like "service", "deployed", and "responsibility". That should help me narrow down the answer.
AL
Alaine 1 year ago
I'd say the answer is A and B. The rain delay and lack of funding are textbook examples of project risks. Gotta love those trick questions, though!
EM
Emeline 1 year ago
↳ replying to Alaine
Absolutely, being aware of potential risks is key to successful project management.
NA
Na 1 year ago
↳ replying to Alaine
I think it's important to always be prepared for unexpected challenges like these.
VI
Virgilio 1 year ago
↳ replying to Alaine
Yeah, the rain delay and lack of funding can really throw a wrench in things.
DA
Daniela 1 year ago
↳ replying to Alaine
I agree, A and B are definitely risks that could impact the project.
WE
Wendell 1 year ago
↳ replying to Alaine
Absolutely, proactive risk management is key to project success.
EL
Elenor 1 year ago
↳ replying to Alaine
I think we need to come up with a plan to mitigate these risks before they become bigger issues.
JA
Janessa 1 year ago
↳ replying to Alaine
Yeah, the rain delay and lack of funding can really throw a wrench in things.
LA
Lai 1 year ago
↳ replying to Alaine
I agree, A and B are definitely risks that could impact the project.
BE
Beckie 1 year ago
Haha, the marketing reps not being ready to take orders after training? That's just plain incompetence, not a risk! I'm going with C on this one.
CA
Carmela 2 years ago
I'm not sure about this one. Unclear requirements seem like an issue to me, but I guess it could also be considered a risk. Hmm, tough call.
KI
Kirk 2 years ago
I'm not sure, I think C could also be a risk.
SH
Sharan 2 years ago
I agree with Thea, A and B are definitely risks.
RO
Rosalyn 2 years ago
I think the answer is A and B. The painting crew delay due to rain and lack of funding approval are clearly risks, not issues.
BE
Beata 1 year ago
↳ replying to Rosalyn
Correct, those are the risks identified in the options provided.
LI
Lindsey 1 year ago
↳ replying to Rosalyn
So, we both think the answer is A and B then.
CH
Charlena 1 year ago
↳ replying to Rosalyn
Yes, and the lack of funding approval is also a risk that could impact the project.
KA
Kathrine 1 year ago
↳ replying to Rosalyn
Yes, those are risks because they could impact the project schedule and success.
MA
Marguerita 1 year ago
↳ replying to Rosalyn
I agree, the painting crew delay and lack of funding approval are definitely risks.
GL
Glory 1 year ago
↳ replying to Rosalyn
I agree, the painting crew delay due to rain is definitely a risk.
TH
Thea 2 years ago
I think the risks are A and B.