Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.
How should you address this?
Suggested Answer: C
Get Premium ASM Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
39 comments · newest first
KI
Kindra
11 months ago
Wait, are we really that bad at estimating?
NA
Narcisa
12 months ago
Completing incomplete Stories might help too.
JO
Jolanda
12 months ago
Not sure about switching to Ideal days, seems risky.
BE
Bettina
12 months ago
Totally agree, some estimates just feel off!
GL
Glen
1 year ago
I think re-estimating all small Stories makes sense.
YA
Yaeko
1 year ago
I feel like completing the incomplete Stories could help us see where we really stand, but I’m not sure if that addresses the estimation issue directly.
ED
Edison
1 year ago
I’m a bit confused about switching to Ideal days. I thought we were supposed to stick with Story Points for better accuracy in Agile.
JO
Joseph
1 year ago
I think we might have practiced a similar question where we had to decide if we should adjust our Velocity. It feels like that could be an option here too.
MA
Maira
1 year ago
I remember we talked about how important it is to keep our estimates consistent, but I'm not sure if re-estimating all the small Stories is the right move.
DA
Dana
1 year ago
This question seems straightforward, I think I can handle it.
OM
Omer
1 year ago
It's confusing because I recall reading about security best practices, but I can't remember if it impacts the notifications directly.
BR
Brice
1 year ago
Hmm, I'm a bit unsure about this one. The question is asking for all the reasons, but some of these options seem similar. I'll need to carefully analyze each one to make sure I don't miss anything.
KA
Katina
1 year ago
Ah, the classic 'my estimates are wrong' problem. I'll take a double order of Option C with a side of 'the team needs better estimation skills'.
LI
Lizette
1 year ago
C) Re-estimate all small Stories
GL
Glenn
1 year ago
B) Increase or re-estimate Velocity
MA
Matthew
1 year ago
C) Re-estimate all small Stories
JO
Josphine
1 year ago
B) Increase or re-estimate Velocity
DU
Dulce
1 year ago
A) Complete incomplete Stories
AN
Angelo
1 year ago
A) Complete incomplete Stories
CE
Cecil
1 year ago
Option D - using Ideal days? What is this, the 90s? Story points are where it's at, my dude. Let's stick with that and tweak the estimates as needed.
LA
Layla
1 year ago
C) Re-estimate all small Stories
SA
Sang
1 year ago
B) Increase or re-estimate Velocity
PE
Peggie
1 year ago
A) Complete incomplete Stories
TU
Tula
1 year ago
I'm with Elenore on this one. Jumping straight to re-estimating everything feels a bit reactive. Let's dig into the root cause first before making any changes.
EL
Elbert
1 year ago
We should focus on improving our estimation process rather than making immediate changes.
AJ
Aja
1 year ago
We could also consider increasing or re-estimating our Velocity to better reflect our progress.
ME
Merilyn
1 year ago
Maybe we can have a discussion with the team to understand why some Stories are not estimated correctly.
CL
Claribel
1 year ago
Maybe we can complete the incomplete Stories first to see if that improves our progress.
NA
Nadine
1 year ago
I agree, we should identify the root cause before jumping to re-estimating everything.
KA
Kasandra
1 year ago
I agree, we should identify the root cause before jumping to re-estimating everything.
MI
Mireya
1 year ago
Let's analyze why some Stories are not estimated correctly before making any changes.
SH
Shala
1 year ago
Let's analyze why some Stories are not estimated correctly before making any changes.
EL
Elenore
1 year ago
I'm all for re-estimating the stories, but don't we need to figure out why the progress is lagging first? Could be an issue with the team's capacity or the story breakdown.
DO
Domingo
2 years ago
Option C seems like the way to go. Reviewing the estimates for the smaller stories could help get a better handle on the overall velocity.
HU
Huey
1 year ago
Let's make sure to adjust our estimates for future sprints to avoid this issue.
KA
Kaitlyn
1 year ago
I agree, re-estimating the smaller stories could give us a clearer picture of our progress.
AV
Avery
2 years ago
I believe we should increase or re-estimate Velocity to address this issue.
FE
Felix
2 years ago
I disagree, we should complete incomplete Stories first.
SC
Scot
2 years ago
I think we should re-estimate all small Stories.