Exin Exam ASM Topic 8 Question 32 Discussion

Actual exam question for Exin's ASM exam
Question #: 32
Topic #: 8
[All ASM Questions]

Your team uses Story Points to estimate User stories.

Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.

How should you address this?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Domingo
2 days ago
Option C seems like the way to go. Reviewing the estimates for the smaller stories could help get a better handle on the overall velocity.
upvoted 0 times
...
Avery
10 days ago
I believe we should increase or re-estimate Velocity to address this issue.
upvoted 0 times
...
Felix
12 days ago
I disagree, we should complete incomplete Stories first.
upvoted 0 times
...
Scot
16 days ago
I think we should re-estimate all small Stories.
upvoted 0 times
...