Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other Stories.
I'm with Elenore on this one. Jumping straight to re-estimating everything feels a bit reactive. Let's dig into the root cause first before making any changes.
I'm all for re-estimating the stories, but don't we need to figure out why the progress is lagging first? Could be an issue with the team's capacity or the story breakdown.