Exin ASM Exam - Topic 7 Question 42 Discussion

Actual exam question for Exin's ASM exam
Question #: 42
Topic #: 7
[All ASM Questions]

The Scrum framework, being an Agile iterative process, inherently minimizes risk. Many Scrum practices

facilitate effective management of risk. Choose the option that is NOT a correct pairing of a Scrum

characteristic with its role in minimizing risk:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Shawna
4 months ago
Wait, is Flexibility really about business-environment risks? Seems off.
upvoted 0 times
...
Michel
4 months ago
Regular feedback is super important for managing expectations!
upvoted 0 times
...
Earlean
4 months ago
Not sure about that Transparency and investment risk pairing.
upvoted 0 times
...
Georgeanna
4 months ago
I think Team ownership is key for estimation risks.
upvoted 0 times
...
Whitney
4 months ago
Flexibility really helps with adapting to changes!
upvoted 0 times
...
Paris
5 months ago
I practiced a similar question about Scrum roles and risks, and I think option C might be the odd one out regarding estimation risk.
upvoted 0 times
...
Adolph
5 months ago
Transparency is crucial for investment risk, but I feel like I might be mixing up some of these pairings.
upvoted 0 times
...
Jeanice
5 months ago
I think regular feedback definitely helps with managing expectations-related risk, but I can't recall how team ownership connects to estimation risk.
upvoted 0 times
...
Shawn
5 months ago
I remember that flexibility is important in Scrum, but I'm not sure if it's specifically tied to business-environment-related risk.
upvoted 0 times
...
Flo
5 months ago
Hmm, I'm a bit unsure on this one. The principles seem to be about the ethical use of AI, so I'm not sure if "lawful" would necessarily be one of them. I might need to re-read the question and options more carefully.
upvoted 0 times
...
Stefan
5 months ago
I'm pretty sure this is False, since Coalesce can use multiple fields to identify a record.
upvoted 0 times
...
Dong
10 months ago
Regular feedback handling expectations-related risk? That makes sense, but I'm still not sure about the correct answer. This Scrum stuff can get confusing sometimes.
upvoted 0 times
Kris
8 months ago
C) Team ownership: Estimation related risk
upvoted 0 times
...
Dell
9 months ago
B) Regular feedback: Expectations-related risk
upvoted 0 times
...
Cherilyn
9 months ago
A) Flexibility: Business-environment-related risk
upvoted 0 times
...
...
Charlesetta
10 months ago
Flexibility and business-environment-related risk? That one seems like a pretty straightforward pairing to me. The others are a bit more debatable.
upvoted 0 times
Diego
9 months ago
B) Regular feedback: Expectations-related risk
upvoted 0 times
...
Leonardo
9 months ago
Leonardo: I agree, flexibility definitely helps with business-environment-related risk.
upvoted 0 times
...
Percy
10 months ago
A) Flexibility: Business-environment-related risk
upvoted 0 times
...
...
Novella
10 months ago
Haha, the 'investment risk' answer is a bit of a stretch. I bet the exam writer just wanted to throw in a curveball there!
upvoted 0 times
...
Paris
10 months ago
Wait, team ownership minimizes estimation-related risk? I thought that was more about accountability and collaboration. This question is tricky!
upvoted 0 times
Aleisha
10 months ago
User 2: I see, so it's not just about accountability but also about making sure everyone is on the same page when it comes to estimating tasks.
upvoted 0 times
...
Alona
10 months ago
User 1: Team ownership actually helps in minimizing estimation-related risk by involving the team in the estimation process.
upvoted 0 times
...
...
Bettyann
11 months ago
Hmm, that's an interesting perspective. Let's discuss further.
upvoted 0 times
...
Karon
11 months ago
I disagree, I believe the correct pairing is D) Transparency: Investment risk.
upvoted 0 times
...
Bettyann
11 months ago
I think the correct pairing is C) Team ownership: Estimation related risk.
upvoted 0 times
...