Posted by Billye on May 08, 2022 at 07:33 AM

A CEO asks the Development Team to add a new item to the Sprint. What should the Development Team do in response?

Suggested Answer: C

Get Premium ASM Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
38 comments · newest first
KI
King 11 months ago
Adding it to the Product Backlog is the right move!
JE
Jenelle 12 months ago
Replacing an item sounds risky, but it could work.
ST
Staci 12 months ago
Surprised the CEO can just ask for changes like that!
AN
Annmarie 12 months ago
I think adding it to the Sprint directly is a bad idea.
RO
Roxanne 1 year ago
They should definitely refer it to the Product Owner.
GR
Gregg 1 year ago
Adding the item to the Product Backlog sounds familiar, but I wonder if that's the best approach in this situation.
ER
Erick 1 year ago
I remember a practice question where we had to decide if we could just add items to the Sprint. I think that's not allowed, right?
CO
Coleen 1 year ago
I think the Development Team should refer it to the Product Owner, but I'm not entirely sure if that's the only option.
TA
Tambra 1 year ago
I feel like replacing an item in the Sprint could be an option, but it seems risky. What if it disrupts our current progress?
VI
Viva 1 year ago
Okay, so Felicia is really paranoid about security and wants to monitor everything. But Celeste seems more laid-back about the risks. I think the consultant will need to walk them through the legal requirements and privacy implications, and help them come up with a reasonable policy that addresses Felicia's concerns without being overly intrusive.
AN
Andrew 1 year ago
I'm leaning towards option A - an open competition with an ITT. That way Mandy can get the widest possible pool of suppliers to choose from. The restricted approach in option B might be a bit limiting.
NI
Nickolas 1 year ago
Okay, let's see. I think the key is to focus on the validation rules for materials. Creating the CHECK_MATERIAL function and enabling the material entity in the data model seem like the right moves.
RI
Rikki 1 year ago
I'm a bit confused by this question. It seems like there are a few different options, and I'm not sure which one is the best approach. I'll need to carefully read through the details and think about the implications of each choice before deciding.
SA
Santos 1 year ago
The CEO must have been watching too many episodes of 'The Office' and thinks they can just waltz in and change the Sprint. Sorry, boss, this isn't Dunder Mifflin!
EV
Eva 1 year ago
↳ replying to Santos
C: Replace an item of the Sprint with the new one
LE
Leigha 1 year ago
↳ replying to Santos
B: Add the item to the Sprint
GL
Glendora 1 year ago
↳ replying to Santos
A: Refer it to the Product Owner
ME
Melvin 2 years ago
The CEO is trying to 'Sprint' into the Development Team's business. The correct answer is to 'Scrum' them off and refer it to the Product Owner.
FR
Freida 1 year ago
↳ replying to Melvin
D: Agreed, let's follow the Scrum process.
GW
Gwen 1 year ago
↳ replying to Melvin
C: We shouldn't just add it to the Sprint without consulting the Product Owner.
IL
Iluminada 1 year ago
↳ replying to Melvin
B: Yeah, that's the right move.
CH
Chun 1 year ago
↳ replying to Melvin
A: Let's refer it to the Product Owner.
VE
Venita 1 year ago
↳ replying to Melvin
D: Okay, let's do that then.
FA
Fanny 1 year ago
↳ replying to Melvin
C: No, we should follow the process and refer it to the Product Owner.
AU
Audria 1 year ago
↳ replying to Melvin
B: But shouldn't we add the item to the Sprint?
PR
Precious 1 year ago
↳ replying to Melvin
A: Let's refer it to the Product Owner.
BA
Barbra 2 years ago
Hmm, let me guess - the CEO wants to 'Scrum' the Development Team by adding a new item. They should just 'Sprint' back to the Product Owner instead.
CH
Chandra 1 year ago
↳ replying to Barbra
B) Add the item to the Sprint
NI
Nickolas 1 year ago
↳ replying to Barbra
A) Refer it to the Product Owner
TU
Tu 2 years ago
The CEO is overstepping their boundaries. The Development Team should add the new item to the Product Backlog, not the Sprint. That's how Scrum works.
SH
Sharee 2 years ago
D) Add the item to the Product Backlog
JO
Joesph 2 years ago
The CEO has no authority to add items to the Sprint. The Development Team should refer it to the Product Owner, who is responsible for managing the Product Backlog.
TA
Tamera 1 year ago
↳ replying to Joesph
The Development Team should focus on the current Sprint goals
ZE
Zena 1 year ago
↳ replying to Joesph
The Sprint should not be changed without the Product Owner's approval
MA
Marylou 1 year ago
↳ replying to Joesph
The Product Owner will prioritize it
WI
Willow 1 year ago
↳ replying to Joesph
Refer it to the Product Owner
SA
Salina 2 years ago
B) Add the item to the Sprint
AN
Angella 2 years ago
A) Refer it to the Product Owner