On a hydroelectric power project, damage to life and property due to floods and landslides has been identifiedas a potential risk. Which of the following Risk Assessment Techniques can be used by the Scrum Team toassess the potential risk, and its impact on project objectives?
A) Probability Impact Grid.
B) Probability Trees.
C) Pareto Analysis.
D) Expected Monetary Value.

Exin ASM Exam - Topic 4 Question 104 Discussion

Actual exam question for Exin's ASM exam
Question #: 104
Topic #: 4
[All ASM Questions]

On a hydroelectric power project, damage to life and property due to floods and landslides has been identified

as a potential risk. Which of the following Risk Assessment Techniques can be used by the Scrum Team to

assess the potential risk, and its impact on project objectives?

Show Suggested Answer Hide Answer
Suggested Answer: A