Which of the following is NOT an objective of a Retrospect Sprint Meeting?
:
Primary objectives of Retrospect Sprint meeting are to identify three specific things:
1. Things the team needs to keep doing: best practices
2. Things the team needs to begin doing: process improvements
3. Things the team needs to stop doing: process problems and bottlenecks
4. These areas are discussed and a list of Agreed Actionable Improvements is created.