Which of the following is NOT an objective of a Retrospect Sprint Meeting?

Show Suggested Answer Hide Answer
Suggested Answer: B

:

Primary objectives of Retrospect Sprint meeting are to identify three specific things:

1. Things the team needs to keep doing: best practices

2. Things the team needs to begin doing: process improvements

3. Things the team needs to stop doing: process problems and bottlenecks

4. These areas are discussed and a list of Agreed Actionable Improvements is created.