Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Exin ASM Exam - Topic 2 Question 102 Discussion

As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length ofSprint is determined keeping in mind the changes expected. Which of the following statements is true in thisregard?
C) If the project is stable, with only minor changes expected, the Length of Sprint should be relatively shorter, 1 to 3 weeks.
A) It is advisable to consider the Release Dates for the overall product or service to determine the Length of Sprint.
B) The impact and frequency of expected changes do not have any impact on the decision related to the Length of Sprint.
D) To get maximum benefits from a Scrum project, it is always recommended to keep the Sprint Time-boxed to 6 weeks.

Exin ASM Exam - Topic 2 Question 102 Discussion

Actual exam question for Exin's ASM exam
Question #: 102
Topic #: 2
[All ASM Questions]

As a Scrum Master, you have to coordinate with the Product Owner to ensure that an appropriate Length of

Sprint is determined keeping in mind the changes expected. Which of the following statements is true in this

regard?

Show Suggested Answer Hide Answer
Suggested Answer: C

:

If project requirements are generally stable and major changes are not expected in the near future, the Length

of a Sprint may be set to be longer, 4 to 6 weeks. This provides stability to the Scrum Team members to work

on the Prioritized Product Backlog requirements for lengthy periods of time without having to go through the

Create User Stories, Approve, Estimate and Commit User Stories, Create Tasks, Estimate Task, and other

related processes that are conducted for every Sprint. However, if project requirements are not very well

defined or if significant changes are expected in the immediate future, the Length of Sprint may be relatively

shorter, 1 to 3 weeks. This provides stability to the Scrum Team members to work on shorter Sprints and

deliver results, which can be evaluated by the Product Owner and stakeholders at the end of the Sprint. This

also provides enough flexibility for them to clarify requirements and make changes to the Prioritized Product

Backlog at the end of each Sprint.


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel