A Scrum team is dividing their work Azis is the Product Owner and has refined the product backlog He wants to assign the tasks to the Developers The Developers want to choose their own tasks The Scrum Master agrees with the Product Owner
Is it a good idea it the Product Owner divides the tasks'?