During a Sprint Planning, a team has picked three User Stories:
Story 1 -- 5 Story Points
Story 2 -- 8 Story Points
Story 3 -- 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.
The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?