During a Sprint Planning, a team has picked three User Stories:

Story 1 -- 5 Story Points

Story 2 -- 8 Story Points

Story 3 -- 3 Story Points

At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these.

The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.

What is the Velocity of this team?

Show Suggested Answer Hide Answer
Suggested Answer: A