A Scrum team failed to meet the Sprint objectives. One of the key members of the team fell ill and was away for two days right at the beginning of the four week Sprint.
What is the most likely reason that the team did not meet the Sprint objectives?
Suggested Answer: C
Get Premium ASF Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
12 comments · newest first
LA
Lawrence
3 months ago
C makes sense. Losing a key member affects planning.
AN
Annette
3 months ago
I agree, but B could be true too. Skills matter.
PA
Pamella
3 months ago
I think it's C. They didn't plan well.
ER
Erasmo
3 months ago
Wait, they only lost one member for two days? That's surprising!
NO
Noelia
4 months ago
I disagree, the Product Owner should have stepped up more.
XU
Xuan
4 months ago
Illness can really throw off a team's momentum, though.
AN
Annett
5 months ago
I think it's more about the team being over-worked.
XO
Xochitl
6 months ago
Sounds like a classic case of poor planning.
DO
Dorinda
6 months ago
I feel like over-worked teams might struggle, but with someone missing, it seems more likely they just didn’t plan well enough.
SH
Shakira
6 months ago
This reminds me of a practice question where we talked about skill gaps in the team. I wonder if that could be a factor here too.
DE
Demetra
7 months ago
I’m not sure, but I think if the team didn’t plan effectively, it could lead to issues like this.
CA
Carmen
7 months ago
I remember discussing how team dynamics can really impact Sprint outcomes, especially if a key member is absent.