You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Thurman
14 days ago
The Risk Management Plan is where it's at. That's the plan that outlines how you'll identify, analyze, and respond to those juicy project risks.
upvoted 0 times
...
Adelaide
17 days ago
Stakeholder management strategy? Maybe if we're running a popularity contest, but this is about communicating project risks.
upvoted 0 times
C) Risk Management Plan
upvoted 0 times
...
Aliza
1 days ago
A) Communications Management Plan
upvoted 0 times
...
Tenesha
3 days ago
A) Communications Management Plan
upvoted 0 times
...
...
Lyndia
1 months ago
Haha, imagine the Risk Management Plan being called the 'Risk Sharing Plan' instead. That would be a giveaway!
upvoted 0 times
Troy
3 days ago
C) Risk Management Plan
upvoted 0 times
...
Nicolette
19 days ago
B) Resource Management Plan
upvoted 0 times
...
Ryann
27 days ago
A) Communications Management Plan
upvoted 0 times
...
...
Lashaunda
1 months ago
The Resource Management Plan? Come on, that's about managing the project team, not communicating risk information to stakeholders.
upvoted 0 times
...
Annice
2 months ago
I'm not sure, but I think C) Risk Management Plan could also be a possible answer.
upvoted 0 times
...
Ines
2 months ago
I agree with Terrilyn. The Communications Management Plan will define who will share information on project risks.
upvoted 0 times
...
Yolando
2 months ago
The Communications Management Plan is the obvious choice here. It defines how project information will be shared with stakeholders, including details on project risks.
upvoted 0 times
Selene
7 days ago
The Risk Management Plan focuses on identifying, analyzing, and responding to project risks, but it doesn't specifically address how information on risks will be shared with stakeholders.
upvoted 0 times
...
Janessa
29 days ago
C) Risk Management Plan
upvoted 0 times
...
Kate
1 months ago
That's correct. The Communications Management Plan outlines how project information, including risks, will be communicated to stakeholders.
upvoted 0 times
...
Laurel
1 months ago
A) Communications Management Plan
upvoted 0 times
...
...
Terrilyn
2 months ago
I think the answer is A) Communications Management Plan.
upvoted 0 times
...

Save Cancel