A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
B) Assess the impact of the request and create a change request
A) Decline because it is not included in the project scope.
C) Create new functional and non-functional requirements for mobile devices.
D) Revise the baseline of the project plan by adding the new requirements.