Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 7 Question 1 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 1
Topic #: 7
[All PK0-005 Questions]

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

Show Suggested Answer Hide Answer

Comments

Currently there are no comments in this discussion, be the first to comment!


Save Cancel