Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
A Sprint Review involves reviewing the completed backlog items and presenting the work to stakeholders. This aligns with CompTIA Project+ agile practices, where a Sprint Review focuses on completed tasks and feedback.