When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Suggested Answer: C
Get Premium PK0-005 Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.
26 comments · newest first
FA
Fausto
1 month ago
True, but critical paths involve tasks with duration. Milestones are the best fit.
JE
Jerlene
1 month ago
But what about A) Critical paths? They are important too.
VA
Valentin
2 months ago
Agreed! Milestones have zero duration. They show progress.
LI
Lili
2 months ago
I think it's C) Milestones. They mark key points.
SI
Simona
2 months ago
Definitely C) Milestones. They help track important events in the project.
MA
Maybelle
2 months ago
I’m torn between A) Critical paths and C) Milestones. But I lean towards C.
IL
Ilene
2 months ago
Agreed! Milestones have zero duration. They show progress.
RO
Rosio
2 months ago
I think it's C) Milestones. They mark key points.
JU
Justine
3 months ago
True, but critical paths involve tasks with duration. Milestones are the right choice.
PE
Penney
3 months ago
But what about A) Critical paths? They are important too.
IZ
Izetta
3 months ago
Agreed! Milestones have zero duration.
IS
Isadora
3 months ago
I think it's C) Milestones. They mark key points.
NE
Nelida
3 months ago
I thought critical paths were the main focus, not milestones.
VI
Vincenza
4 months ago
Definitely milestones, they mark important points.
RI
Rikki
5 months ago
Wait, zero duration? That sounds odd.
KR
Kristel
5 months ago
Totally agree, milestones are key.
TI
Tijuana
5 months ago
Those are called milestones!
MA
Mabel
6 months ago
Totally agree, milestones are key in scheduling!
JE
Jennifer
6 months ago
Wait, zero duration? That sounds weird...
DE
Dell
6 months ago
Definitely milestones, no doubt about it.
LA
Laquita
6 months ago
I thought they were critical paths?
KR
Krystal
6 months ago
Those are called milestones!
CE
Ceola
6 months ago
I’m a bit lost on this one. I thought resources were related to tasks, not zero duration activities.
ET
Ettie
7 months ago
Milestones sound familiar for zero duration activities, especially from that practice question we did last week.
DA
Danica
7 months ago
I remember something about critical paths, but I don't think that's the right answer for zero duration activities.
CH
Christiane
7 months ago
I think activities with zero duration are often referred to as milestones, but I'm not entirely sure.