Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CompTIA Exam PK0-005 Topic 1 Question 49 Discussion

Actual exam question for CompTIA's PK0-005 exam
Question #: 49
Topic #: 1
[All PK0-005 Questions]

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Noah
7 days ago
I agree with Chana. It's important to adjust the timeline based on the new dependency.
upvoted 0 times
...
Chana
8 days ago
I think the project manager should work with the project scheduler to update the timeline.
upvoted 0 times
...

Save Cancel