A manager must select one of three projects, W, X or Y.
The following payoff table has been prepared to show the outcomes in $000 at three possible levels of demand:

The manager is now preparing a regret matrix.
What figure (in $000) will be shown for Project Y in the regret matrix if the average demand arises?
References:
Leanora
4 months agoTalia
4 months agoCherry
4 months agoIsabella
4 months agoTarra
4 months agoPaulene
5 months agoJohnetta
5 months agoLemuel
5 months agoNobuko
5 months agoCarlota
5 months agoMargret
5 months agoJonelle
10 months agoRosalind
9 months agoSalley
9 months agoDortha
9 months agoJanella
10 months agoShayne
10 months agoJade
9 months agoGlen
9 months agoMilly
9 months agoKendra
10 months agoAlica
10 months agoTheron
8 months agoAdelina
8 months agoDino
8 months agoSherell
8 months agoBambi
8 months agoNovella
9 months agoMatthew
10 months agoCarisa
10 months agoYoulanda
10 months agoCharlene
10 months agoYoulanda
11 months ago