A manager must select one of three projects, W, X or Y.

The following payoff table has been prepared to show the outcomes in $000 at three possible levels of demand:

The manager is now preparing a regret matrix.

What figure (in $000) will be shown for Project Y in the regret matrix if the average demand arises?

Show Suggested Answer Hide Answer
Suggested Answer: A

References:


Contribute your Thoughts:

0/2000 characters
Leanora
4 months ago
Just checked, and yeah, 150 is correct for Project Y!
upvoted 0 times
...
Talia
4 months ago
Wait, are we sure about that 150 figure? Seems off.
upvoted 0 times
...
Cherry
4 months ago
Totally agree, 150 makes sense based on the table!
upvoted 0 times
...
Isabella
4 months ago
I think the regret for Y should be 150, right?
upvoted 0 times
...
Tarra
4 months ago
Project Y has a payoff of 110 at average demand.
upvoted 0 times
...
Paulene
5 months ago
I think I saw that the regret for Project Y at average demand should be calculated against the maximum payoff for that demand level. I just can’t remember the exact numbers!
upvoted 0 times
...
Johnetta
5 months ago
I feel a bit confused about which demand level to use for Project Y. Was it the middle one? I hope I can remember the payoff values correctly.
upvoted 0 times
...
Lemuel
5 months ago
If I recall correctly, the regret is the difference between the best outcome and the outcome of the project chosen. I think I need to look at the average demand row for Project Y.
upvoted 0 times
...
Nobuko
5 months ago
I remember we practiced a similar question about regret matrices, but I’m not sure how to calculate the regret for Project Y specifically.
upvoted 0 times
...
Carlota
5 months ago
Okay, I know NX-API is used for Cisco Nexus switches, so I should be able to figure this out. Let me think through the common network management commands.
upvoted 0 times
...
Margret
5 months ago
Okay, I've got a strategy - I'll carefully read through each answer option and think about how the item master and sales order processing would work in each case.
upvoted 0 times
...
Jonelle
10 months ago
This question is so dry, it's making me thirsty! Maybe the manager should just flip a coin and call it a day. But if I had to guess, I'd say the regret for Project Y in the average demand scenario is $160,000. Option D FTW!
upvoted 0 times
Rosalind
9 months ago
Yeah, $160,000 for Project Y in the regret matrix makes sense. Let's see if the manager goes with that option.
upvoted 0 times
...
Salley
9 months ago
I agree, Option D seems like the best choice here. Let's hope the manager makes the right decision.
upvoted 0 times
...
Dortha
9 months ago
I think you're right, the regret for Project Y in the average demand scenario is $160,000. Option D is the way to go!
upvoted 0 times
...
...
Janella
10 months ago
Regret matrix, huh? Sounds like a band name. Or maybe a new cryptocurrency. Anyway, I'm going with option C. $520,000 sounds like a pretty good payoff to me, even if it's not the maximum. Hey, at least I'm not the one who has to make the tough decisions around here!
upvoted 0 times
...
Shayne
10 months ago
Ah, the age-old question of which project to choose. This is like trying to pick a winner at the horse races - you never know for sure until the race is run! But I think I've got it figured out. The regret for Project Y when average demand arises is $160,000, so option D is the correct answer.
upvoted 0 times
Jade
9 months ago
So, the manager should probably avoid choosing Project Y if the average demand arises.
upvoted 0 times
...
Glen
9 months ago
That makes sense, Project Y seems to have the highest regret at average demand.
upvoted 0 times
...
Milly
9 months ago
I think you're right, the regret for Project Y at average demand is $160,000.
upvoted 0 times
...
...
Kendra
10 months ago
I'm not sure about this one. The payoff table shows the outcomes, but I'm having a hard time figuring out how to calculate the regret matrix. Maybe I should have paid more attention in my decision-making class.
upvoted 0 times
...
Alica
10 months ago
Well, this is a tricky one. If average demand arises, then the payoff for Project Y is $520,000, which is the highest among the three projects. So, the regret for Project Y would be the difference between this and the maximum payoff, which is $160,000. Option C is the correct answer.
upvoted 0 times
Theron
8 months ago
Exactly, the regret for Project Y is 160.
upvoted 0 times
...
Adelina
8 months ago
Oh, I see. So, the regret for Project Y would be 160.
upvoted 0 times
...
Dino
8 months ago
No, it's not 520. The correct answer is 160.
upvoted 0 times
...
Sherell
8 months ago
I think the answer is 520.
upvoted 0 times
...
Bambi
8 months ago
Oh, I see. Thanks for clarifying.
upvoted 0 times
...
Novella
9 months ago
Actually, it's 520. The regret for Project Y would be 160.
upvoted 0 times
...
Matthew
10 months ago
No, I believe it's 110.
upvoted 0 times
...
Carisa
10 months ago
I think the answer is 520.
upvoted 0 times
...
...
Youlanda
10 months ago
Why do you think it's 160?
upvoted 0 times
...
Charlene
10 months ago
I disagree, I believe the correct answer is D) 160.
upvoted 0 times
...
Youlanda
11 months ago
I think the answer is A) 150.