A manager must select one of three projects, W, X or Y.The following payoff table has been prepared to show the outcomes in $000 at three possible levels of demand:The manager is now preparing a regret matrix.What figure (in $000) will be shown for Project Y in the regret matrix if the average demand arises?
A) 150
B) 110
C) 520
D) 160

CIMAPRO19-P01-1 Exam - Topic 5 Question 128 Discussion

Actual exam question for CIMA's CIMAPRO19-P01-1 exam
Question #: 128
Topic #: 5
[All CIMAPRO19-P01-1 Questions]

A manager must select one of three projects, W, X or Y.

The following payoff table has been prepared to show the outcomes in $000 at three possible levels of demand:

The manager is now preparing a regret matrix.

What figure (in $000) will be shown for Project Y in the regret matrix if the average demand arises?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Cecil
11 days ago
I feel confident about A) 150. It seems like the right choice.
upvoted 0 times
...
Gilma
16 days ago
I agree with Jamie. Regret matrix shows missed opportunities.
upvoted 0 times
...
Kizzy
21 days ago
I think it's B) 110. Project Y has lower payoffs at average demand.
upvoted 0 times
...
Geoffrey
26 days ago
This question is tricky. I feel unsure about the regret matrix.
upvoted 0 times
...
Ethan
1 month ago
I don't know, I thought it would be higher than that.
upvoted 0 times
...
Aja
1 month ago
Totally agree, 150 sounds right!
upvoted 0 times
...
Dudley
1 month ago
Wait, are we sure about that? Seems off to me.
upvoted 0 times
...
Pearlene
2 months ago
I think it's actually 150 for Project Y.
upvoted 0 times
...
Ashlyn
2 months ago
Project Y has a payoff of 110 at average demand.
upvoted 0 times
...
Georgeanna
2 months ago
I think I remember that the regret for Project Y at average demand could be 150, but I’m not confident. I need to double-check the payoffs again to be sure.
upvoted 0 times
...
Daniela
2 months ago
If I recall correctly, for average demand, we should look at the payoffs for all projects and find the maximum for that demand level. Then subtract Project Y's payoff from it.
upvoted 0 times
...
Amos
2 months ago
I’m not entirely sure how to calculate the regret matrix. I think it involves finding the difference between the best outcome and the outcome for Project Y, but I’m confused about the average demand level.
upvoted 0 times
...
Gayla
2 months ago
I remember we practiced a similar question with a payoff table and had to calculate regrets. I think the regret for Project Y might be related to the highest payoff in that demand scenario.
upvoted 0 times
...

Save Cancel