A decision tree is being evaluated back to a decision point.
There are two alternatives at this point:
1. To abandon the project and generate a return of $435,000;
2. To continue with the project and generate the following possible returns:

What value should be included at the decision point?
References:
Victor
10 months agoLeeann
10 months agoTonette
10 months agoAdelle
10 months agoLazaro
10 months agoDelbert
11 months agoSalome
11 months agoMelda
11 months agoIsabella
11 months agoJoni
11 months agoElena
11 months agoGlendora
11 months agoBuck
11 months agoJestine
11 months agoLelia
11 months agoKaran
11 months agoMing
11 months agoViola
11 months agoMaybelle
11 months agoLindsey
11 months agoCasie
1 year agoCharlene
1 year agoStefany
1 year agoJackie
1 year agoMitsue
1 year agoArt
1 year agoTonette
1 year agoTiffiny
1 year agoDusti
1 year agoPhil
1 year agoKandis
1 year agoLorrie
1 year agoSelma
1 year agoCarmen
1 year agoMichael
1 year agoAnnmarie
1 year agoElouise
1 year agoGaston
1 year agoRachael
1 year agoGeraldine
1 year agoVicky
1 year agoMichael
1 year ago