Question #: 73
Topic #: 10
[All CIMAPRO19-P01-1 Questions]

The labour requirement for a special contract is 250 skilled labour hours paid at $10 per hour and 750 semi-skilled labour hours paid at $8 per hour.

At present, skilled labour is fully utilised on other contracts which generate a $12 contribution per hour, after charging labour costs. Additional skilled labour is unavailable in the short term.

There is a surplus of 1,200 semi-skilled hours over the period of the contract but the firm has a policy of no redundancies.

The relevant cost of labour for the special contract is:

Show Suggested Answer Hide Answer
Suggested Answer: A, B, D

References:


Contribute your Thoughts:

Dana
2 days ago
I see both points, but I think the answer is D) $11,500 because we need to factor in the contribution per hour from other contracts.
upvoted 0 times
...
Christoper
8 days ago
I disagree, I believe the answer is C) $8,500 because we need to consider the opportunity cost of using skilled labour on other contracts.
upvoted 0 times
...
Jacinta
12 days ago
I think the answer is B) $3,000 because we have a surplus of semi-skilled hours.
upvoted 0 times
...