CIMAPRA19-F02-1 Exam - Topic 1 Question 54 Discussion
Which of the following examples of contracts will use cost of sales as the balancing figure when calculating profit or loss?Select ALL that apply.
C) Contract A has a total value of75m, costs to date of61m and expected costs to completion of20m. The contracts % stage of completion was calculated by dividing its value to date of45m by75m. and D) Contract A has a total value of60m, costs to date of42m and expected costs to completion of15m. The project's % stage of completion is 80% using the value method.
A) Contract A has a total value of50m, costs to date of42m and expected costs to completion of15m. The project's % stage of completion is 74% using the cost method.
B) Contract A has a total value of55m, costs to date of33m and expected costs to completion of18m.
E) Contract A has a total value of85m, costs to date of69m and expected costs to completion of22m. The contracts % stage of completion was calculated by dividing its costs incurred to date of69m by 75m.
Desire
8 months agoBettina
9 months agoElvera
9 months agoMirta
9 months agoCordell
9 months agoDomonique
9 months agoCasandra
9 months agoStanford
9 months agoWalton
10 months agoLisandra
10 months agoKaty
10 months agoSherell
10 months agoVerlene
10 months ago