CIMAPRA19-E03-1 Exam - Topic 5 Question 3 Discussion
D is aProjectManager. D has just left a meeting with the Executive Team of his Organization. D is delighted that the Executive Team has given support to D's proposal to implement a knowledge management system in the Organization.What should be the next activity that D undertakes in this project?
A) Create a technological infrastructure of hardware and software.
B) Create database structures to store and reference knowledge.
C) Gain the commitment of senior management to the project.
D) Populate the knowledge management system with knowledge.